Contract No: HK/2015/01 Wanchai Development Phase II and Central Wanchai
Bypass Sampling, Field Measurement and Testing Works (Stage 3) Environmental Permit no. EP-356/2009, Further
Evironmental permit nos. fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009 ,
Fep-06/356/2009, FEP-07/356/2009 and Fep-08/356/2009 Monthly
Environmental Monitoring & Audit Report
-
February 2017 -
|
CLIENTS: |
|
Civil Engineering and Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre
Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
March
2017 |
|
|
2.2 Scope of the Project and Site
Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact
Personnel
3 Status of
Regulatory Compliance
3.1 Status of Environmental Licensing and
Permitting under the Project
5.3 Water quality monitoring Results
6.4 Review of the Reasons for and the
Implications of Non-compliance
6.5 Summary of action taken in the event
of and follow-up on non-compliance
7. Cumulative Construction Impact due to
the Concurrent Projects
9.
Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table I Summary of Water Quality Monitoring
Exceedances in Reporting Month
Table II Summary of Enhanced Dissolved Oxygen
Monitoring Exceedances in Reporting Month
Table 2.1 Schedule 2 Designated Projects under
this Project
Table 2.2 Details of Individual Contracts under
the Project
Table 2.3 Contact Details of Key Personnel
Table 3.2 Cumulative Summary of Valid Licences
and Permits under Contract no. HK/2009/01
Table 3.3 Summary of submission status under
FEP-02/356/2009 Condition
Table 3.4 Cumulative Summary of Valid Licences
and Permits under Contract no. HK/2009/02
Table 3.5 Summary of submission status under
FEP-03/356/2009 Condition
Table 3.6 Cumulative Summary of Valid Licences
and Permits under Contract no. HY/2009/15
Table 3.7 Summary of submission status under
FEP-04/356/2009 Condition
Table 3.8 Cumulative Summary of Valid Licences
and Permits under Contract no. HY/2009/19
Table 3.9 Cumulative Summary of
Valid Licences and Permits under Contract no. HK/2012/08
Table
3.10 Summary of submission
status under EP-356/2009 & FEP-06/356/2009 Condition
Table
3.11 Cumulative Summary of
Valid Licences and Permits under Contract no. HY/2010/08
Table
3.12 Summary of submission
status under EP-356/2009 and FEP-07/356/2009 Condition
Table 4.1 Noise Monitoring Station
Table 4.2 Air Monitoring Station
Table 4.3 Marine Water Quality Stations for Water Quality
Monitoring
Table 4.4 Marine Water Quality Monitoring
Frequency and Parameters
Table 4.5 Marine Water Quality Stations for Enhanced Water Quality
Monitoring
Table 5.1 Noise Monitoring Station for Contract
nos. HK/2009/01, HK/2009/02
Table 5.2 Noise Monitoring Station for Contract
no. HY/2009/15
Table 5.3 Noise Monitoring Station for Contract
no. HY/2009/19
Table 5.4
Noise Monitoring Station for Contract no. HY/2010/08
Table 5.5
Air Monitoring Station for Contract no. HK/2009/01
Table 5.6 Air Monitoring Station for Contract
no. HK/2009/02
Table 5.7 Air Monitoring Station for Contract
no. HY/2009/15
Table 5.8 Air Monitoring Stations for Contract
no. HY/2009/19
Table 5.9 Air Monitoring Stations for Contract no.
HK/2012/08
Table 5.10 Air Monitoring Stations for Contract no. HY/2010/08
Table 5.12 Water quality monitoringStations for
Contract no. HK/2009/01
Table 5.13 Water quality monitoringStations for
Contract no. HK/2009/02
Table 5.14 Water quality monitoringStations for Contract no. HK/2012/08
Table 5.15 Water quality monitoringStations for Contract no.
HY/2009/15
Table 5.16 Enhanced Dissolved Oxygen Monitoring Stations for Contract no.
HY/2009/15
Table 5.17 Water quality monitoring Station for Contract no. HY/2010/08
Table 5.18 Enhance Dissolved Oxygen Monitoring Stations for
Contract no. HY/2010/08
Table 5.19 Details of Waste Disposal for Contract no. HK/2009/01
Table 5.20 Details of Waste Disposal for Contract no. HK/2009/02
Table 5.21 Details of Waste Disposal for Contract
no. HY/2009/15
Table 5.22 Details of Waste Disposal for Contract
no. HY/2009/19
Table 5.23 Details of Waste Disposal for Contract
no. HK/2012/08
Table 5.24 Details of Waste Disposal for Contract
no. HY/2010/08
Table 8.1 Summary of Environmental Inspections
for Contract no. HK/2009/01
Table 8.2 Summary of Environmental Inspections for Contract no.
HK/2009/02
Table 8.3 Summary of
Environmental Inpsections for Contract no. HY/2009/15
Table 8.4 Summary of Environmental Inspections for Contract no.
HY/2009/19
Table 8.5 Summary of
Environmental Inspections for Contract no. HK/2012/08
Table 8.6 Summary of
Environmental Inspections for Contract no. HY/2010/08
Table 9.1 Cumulative Statistics on Complaints
Table 9.2 Cumulative Statistics on Successful
Prosecutions
Table 10.1 Construction Activities and
Recommended Mitigation Measures in Coming Reporting Month
lIST OF FIGUREs
Figure 2.2 Project Organization
Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation
Implementation Schedule
Appendix 4.1 Action
and Limit Level
Appendix 4.2 Copies
of Calibration Certificates
Appendix 5.1 Monitoring Schedule for
Reporting Month and Coming month
Appendix 5.2 Noise Monitoring Results and
Graphical Presentations
Appendix 5.3 Air Quality Monitoring
Results and Graphical Presentations
Appendix 5.4 Water Quality Monitoring
Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Summary for Notification of Exceedance
Appendix 10.1 Construction Programme of
Individual Contracts
EXECUTIVE
SUMMARY
i.
This is the Environmental Monitoring and
Audit (EM&A) Monthly Report – February 2017 for the Project of Wan Chai Development Phase II
and Central-Wanchai Bypass under Environmental Permit no. EP-356/2009 and Further
Environmental permit nos. FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009,
FEP-06/356/2009, FEP-07/356/2009 and FEP-08/356/2009. This report presents the environmental
monitoring findings and information recorded during the period of 27th January
2017 to 26th February 2017. The cut-off date of reporting is at
26th of each reporting month.
Construction
Activities for the Reported Period
ii.
During this reporting period, the major work
activities for Contract no. HK/2009/01 included:
·
Nil
iii.
During this reporting period, the major work
activities for Contract no. HK/2009/02 included:
Nil
iv.
During this reporting period, the major work
activities for Contract no. HY/2009/15 included:
·
Reinstatement of Eastern Breakwater
v.
During this reporting period, the major work
activities for Contract no. HY/2009/19 included:
Nil
vi.
During this reporting period, the major work
activities for Contract no. HK/2012/08 included:
·
Installation of Box 1 unit
·
Construction of culver L Bay 8
vii.
During this reporting period, the major work activities
for Contract no. HY/2010/08.
·
Diversion pipe maintenance
·
Preparation for Diaphragm Wall Removal Works
Noise Monitoring
viii.
With respect to the
shift in major construction site portions at Wan Chai North, the noise
monitoring station M1a – Harbour Sports Centre was finely adjusted from East of
Harbour Road Sports Centre to West of Harbour Road Sports Centre on 21 June
2016.
ix.
School examination
was scheduled to be taken place at Henrietta Secondary School from 6 February
2017 to 21 February 2017, the limit level of noise monitoring at station M6 was
adjusted to 65dB(A) during examination period accordingly.
x.
Three limit level exceedances were recorded
at M6 – HK Baptist Church Henrietta School on 7, 13 and 21 February 2017 in the
reporting month. The exceedances were concluded as non-Project related.
xi.
Noise monitoring during daytime and
restricted hour were conducted at the stations M1a, M2b, M3a, M4b, M5b and M6
on a weekly basis in the reporting month.
Air Quality
Monitoring
xii.
Due to interruption
of electricity supply, the 24hr TSP was rescheduled as follows:
CMA1b were
rescheduled from 01 and 13 February 2017 to 02 and 14 February 2017
respectively
CMA3a were
rescheduled from 13 February 2017 to 14 February 2017.
xiii.
One 1hr TSP action
level exceedance was recorded at CMA5b – Pedestrian Plaza on 2 February 2017 in
the reporting month. The exceedance was concluded to be non-Project related.
xiv.
One 24hr TSP action level exceedance was
recorded at CMA5b – Pedestrian Plaza on 18 February 2017 in the reporting
month. The exceedance was concluded to be non-Project related.
xv.
With respect to the proposed demolition of
eastern podium of Oil Street Site Office, the respective air quality monitoring
station CMA1b – Oil Street Site Office was finely adjusted from East podium of
the Oil Street Site Office to the West podium of the Oil Street Site Office on
21 December 2016.
xvi.
1-hour and 24-hour Total Suspended
Particulates (TSP) monitoring were conducted at CMA1b – Oil Street Site Office;
CMA2a – Causeway Bay Community Center; CMA3a – CWB PRE Site Office Area; CMA4a
– Society for the Prevention of Cruelty to Animals; CMA5b – Pedestrian Plaza;
CMA6a – WDII PRE Site Office in the reporting month.
Water Quality
Monitoring
xviii.
With respect to the reinstatement of the silt
screen system for Cooling Water Intakes P7, P8, P9 and WSD Water Intake RW21,
the respective water quality monitoring was reverted to the previous monitoring
location for Water Quality Monitoring Station RW21-P789 from water quality
stations RW21-P789 East (RW21-P789E) and RW21-P789 West (RW21-P789W) from 25
January 2017 onwards.
xix.
With respect to the removal of silt screen at
WQM station RW21-P789 on 26 November 2016, the respective water quality
monitoring at RW21-P789 was adjusted to RW21-P789E and RW21-P789W since 28
November 2016 ebb-tide.
xx.
With respect to the temporarily suspension of
marine construction works at WCR3 Area by Contract HK/2009/02, the installed
silt screen for intake group (P7, P8, P9 and WSD21) was removed on 26 November
2016.
xxi.
As advised by the Contractor of HK/2009/01,
all silt screen remains removal works at P1, P3, P4, P5 and C1 water quality
monitoring stations were completed on 8 May 2016.
xxii.
With respect to the marine works undertaken
at WCR3 by Contract HK/2009/02, the respective water quality monitoring station
C1 associated with Contract HK/2009/01 was updated as in association with
Contract HK/2009/01 and Contract HK/2009/02.
xxiii.
With respect to the marine works undertaken
at CBTS by Contract HY/2010/08, the respective water quality monitoring station
C7 associated with Contract HY/2009/15 was updated as in association with
Contract HY/2009/15 and Contract HY/2010/08.
xxiv.
With respect to the marine works undertaken
at HKCEC2 by Contract HK/2012/08, the respective water quality monitoring
station WSD19, P1, P3, P4, and P5 were associated with Contract HK/2012/08.
Table I Summary of Water Quality Monitoring
Exceedances in Reporting Month
Water quality monitoring Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
||||||||
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
||
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2012/08 |
WSD19 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
P1 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
P3 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
P4 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
P5 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/02 |
RW21-P789 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HY/2009/15 & HY/2010/08 |
C7 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Total |
0 |
0 |
2 |
1 |
1 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
- 4-week post construction water quality
monitoring at WSD9, WSD10, WSD15 and WSD17 were completed on 6 Feb 2012 and the
water quality monitoring at WSD 10 and WSD15 were temporary suspended since 8
Feb 2012, and WSD9 and WSD17 was implemented with respect to HK/2009/02 from 8
Feb 2012 onwards.
- C8 and C9 were implemented with
respect to HY/2009/19 from 28 Jan 2012.
- C8 & C9
were temporary suspended since 4 March 2013.
- WSD7 and WSD20 water quality
monitoring were temporarily suspended from 27 Apr 2012.
-
C2, C3 C4e and
C4w water quality monitoring station was temporarily suspended since 22 Apr
2013
-
P1, P3, P4 and P5
were commenced since 24 Apr 2013
- C5e and C5w
water quality monitoring station was temporarily suspended since 29 Jul 2013.
- WSD21 water
quality monitoring station was temporarily suspended since 12 Mar 2014
- WSD9 and
WSD17 water quality monitoring station was temporarily suspended since 8 Sep
2014 flood tide.
- The water quality monitoring station C1 shall be
associated with Contract No. HK/2009/02 upon commencement of marine works under
DP3 at WCR3 area.
- The water quality monitoring station
RW21-P789 was adjusted to RW21-P789E and RW21-P789W since 28 November 2016 ebb-tide.
- The water quality monitoring was
reverted to previous monitoring station RW21-P789 from PW21-P789E and
RW21-P789W from 25 January 2017 onwards.
xxv.
There were 3 action level and 2 limit level of
turbidity exceedances and 1 action level of suspended solid exceedances recorded
in the reporting month.
xxvi.
Investigation found that the turbidity and
suspended solid exceedances recorded in this reporting month were not related
to Project works. The details of the recorded exceedance can be referred to the
Section
6.4.
xxvii.
Enhanced DO monitoring at 3 monitoring
stations in Causeway Bay Typhoon Shelter and Ex-Public Cargo Works Area was
conducted three days per week during the reporting period. The action and limit
level exceedances of water quality monitoring are summarized in Table
II.
Table II Summary
of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month
|
|
Water
quality monitoring Station |
Mid-flood |
Mid-ebb |
||
|
Contract
no. |
DO |
DO |
|||
|
|
AL |
LL |
AL |
LL |
|
|
C6 |
0 |
0 |
0 |
0 |
|
|
HY/2009/15 |
Ex-WPCWA SW |
0 |
0 |
0 |
0 |
|
|
Ex-WPCWA SE |
1 |
0 |
0 |
0 |
|
Total |
1 |
0 |
0 |
0 |
|
Remarks:
1.
Enhanced DO monitoring at Windsor House Cooling (Station Ref: C7) was
temporarily suspended since 22 October 2014 with respect to the formation of temporary
reclamation zone TS3 and to be resumed upon removal of the respective temporary
reclamation zone.
2. Enhanced
DO monitoring at Monitoring station Ex-WPCWA SE was temporarily suspended from
31 August 2015 with respect to seawall reinstatement works and formation of
active works area. The Enhance DO monitoring at Ex-WPCWA SE was resumed on 11
May 2016 due to completed section of seawall reinstatement works at Ex-PCWA.
xxviii.
There was 1 action level exceedance recorded
for enhanced dissolved oxygen monitoring in this reporting month. Investigation
found that the exceedances recorded in this reporting month were not related to
Project works. The details of the recorded exceedances can be referred to the Section
6.4.
Complaints,
Notifications of Summons and Successful Prosecutions
xxix.
There was no environmental complaint received
in this reporting month.
Site Inspections
and Audit
xxx.
The Environmental Team (ET) conducted weekly
site inspections for Contract nos. HK/2009/01, HK/2009/02, HY/2009/15, HY/2009/19,
HK/2012/08 and HY/2010/08 under EP no. EP-356/2009 in the reporting month.
Major observations and recommendations made during the audit sessions were
rectified by the Contractors. No non-conformance was identified during the site
inspections.
Future Key Issues
xxxi.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
Contract no.
HK/2009/01 – Wan Chai Development Phase II – Central –Wanchai Bypass at HKCEC
Nil
Contract no.
HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai
East
·
Nil
Contract no.
HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter
Section)
·
Nil
Contract no.
HY/2009/19- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern
Corridor Link
Contract no. HK/2012/08 – Wan Chai Development
Phase II – Central- Wan Chai Bypass at Wan Chai West
·
Construction of Box 1 unit
·
Construction of culvert L Bay 8
Contract no. HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip
Road 8)
·
Diversion pipe maintenance
·
Preparation for Diaphragm Wall Removal works
1.1.1.
Lam Geotechnics Limited (LGL) has been
appointed to work as the Environmental Team (ET) under Environmental Permit no.
EP-356/2009 and Further Environmental permit nos. FEP-02/356/2009, FEP-03/356/2009,
FEP-04/356/2009, FEP-06/356/2009, FEP-07/356/2009 and FEP-08/356/2009 to
implement the Environmental Monitoring and Audit (EM&A) programme as
stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai
Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the
approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor
Link (Register No. AEIAR-041/2001).
1.1.2.
This report presents the environmental
monitoring and auditing work carried out in accordance to the Section 10.3 of
EM&A Manual and “Environmental Monitoring and Audit Requirements”
under Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A
works for Environmental Permit no. EP-356/2009, Further Environmental Permit
no. FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009, FEP-06/356/2009, FEP-07/356/2009
and FEP-08/356/2009 during the period of 27th January 2017 to 26th February 2017. The
cut-off date of reporting is at 26th of each reporting month.
Section 1 Introduction – details the scope and structure of the
report.
Section 2 Project
Background – summarizes
background and scope of the project, site description, project organization and
contact details of key personnel during the reporting period.
Section 3 Status of
Regulatory Compliance – summarizes the status of valid Environmental Permits / Licenses
during the reporting period.
Section 4 Monitoring
Requirements – summarizes
all monitoring parameters, monitoring methodology and equipment, monitoring
locations, monitoring frequency, criteria and respective event and action plan
and monitoring programmes.
Section 5 Monitoring
Results – summarizes
the monitoring results obtained in the reporting period.
Section 6 Compliance Audit – summarizes the auditing of monitoring results, all
exceedances environmental parameters.
Section 7 Cumulative
Construction Impact due to the Concurrent Projects – summarizes the
relevant cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section 8 Environmental
Site Audit – summarizes
the findings of weekly site inspections undertaken within the reporting period,
with a review of any relevant
follow-up actions within the
reporting period.
Section 9 Complaints,
Notification of summons and Prosecution – summarizes the cumulative
statistics on complaints, notification of summons and prosecution
Section 10 Conclusion
2.1.1.
“Wan Chai Development phase II and
Central-Wan Chai Bypass” and “Central-Wan Chai Bypass and Island Eastern
Corridor Link” (hereafter called “the Project”) are Designed Project (DP) under
the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The
Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai
Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008)
have been approved on 31 August 2001 and 11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase
II (WDII) is to provide land at Wan Chai North and North Point for construction
of the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land
formed under the project will be developed as a world-class waterfront
promenade joining that at the new Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for
the CWB to provide relief to the very congested east-west Connaught Road
Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is
currently operating beyond its capacity. The CWB will provide relief to the
existing congestion along the Corridor and cater for the anticipated growth of
traffic on Hong Kong Island. Without the CWB and its access roads, there will
not be sufficient capacity to serve the heavy traffic demands at both strategic
and local levels.
2.2.1.
The Project is located mainly in Wan Chai
North, Causeway Bay and North Point, and is demarcated by Gloucester Road and
Victoria Park Road to the south, Fenwick Pier Street to the west and Tong Shui
Road Interchange to the east, as shown in Figure 2.1.
2.2.2.
The study area encompasses existing
developments along the Wan Chai, Causeway Bay and North Point shorelines. Major
land uses include the Hong Kong Convention & Exhibition Centre (HKCEC)
Extension, the Wan Chai Ferry Pier, the ex-Wan Chai Public Cargo Working Area
(ex-PCWA), the Royal Hong Kong Yacht Club (RHKYC), the Police Officers’ Club,
the Causeway Bay Typhoon Shelter (CBTS) and commercial and residential
developments.
2.2.3.
The scope of the
Project comprises:
·
Land formation for key transport
infrastructure and facilities, including the Trunk Road (i.e. CWB) and the
associated slip roads for connection to the Trunk Road and for through traffic
from Central to Wan Chai and Causeway Bay. The land formed for the above transport
infrastructure will provide opportunities for the development of an attractive
waterfront promenade for the enjoyment of the public
·
Reprovisioning / protection of the existing
facilities and structures affected by the land formation works mentioned above
·
Extension, modification, reprovisioning or
protection of existing storm water drainage outfalls, sewerage outfalls and
watermains affected by the revised land use and land formation works mentioned
above
·
Upgrading of hinterland storm water drainage
system and sewerage system, which would be rendered insufficient by the land
formation works mentioned above
·
Provision of the ground level roads,
flyovers, footbridges, necessary transport facilities and the associated
utility services
·
Construction of the new waterfront promenade,
landscape works and the associated utility services
·
The Trunk Road (i.e. CWB) within the study
area and the associated slip roads for connection to the Trunk Road.
2.2.4.
The project also contains various Schedule 2
DPs that, under the EIAO, require Environmental Permits (Eps) to be granted by
the DEP before they may be either constructed or operated. Table 2.1
summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1 Schedule
2 Designated Projects under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB)
including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and
A.7 |
Trunk road and road tunnel
more than 800 m in length |
DP2 |
Road P2 and other roads
which are classified as primary/district distributor roads |
Schedule 2, Part I, A.1 |
Primary / district
distributor roads |
DP3 |
Reclamation works including
associated dredging works |
Schedule 2, Part I, C.1 and
C.12 |
Reclamation more than 5 ha
in size and a dredging operation less than 100 m from a seawater intake point
|
DP5 |
Wan Chai East Sewage Outfall
|
Schedule 2, Part I, F.5 and
F.6 |
Submarine sewage pipelines
with a total diameter more than 1,200 mm and include a submarine sewage
outfall |
DP6 |
Dredging for the
Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less
than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the
Project, there are a number of contracts sub-dividing the whole works area into
different work areas to be commenced. Contractors of individual contracts will
be required by the EP holder to apply Further Environmental Permits (FEP) such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A
reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are
summarized in Table 2.2.
Table 2.2 Details
of Individual Contracts under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HK/2009/01 |
Wan Chai Development Phase
II – Central –Wanchai Bypass at Hong Kong Convention and Exhibition Centre |
DP3, DP6 |
23 July 2010 |
DP1, DP2 |
25 August 2011 |
||
HK/2009/02 |
Wan Chai Development Phase
II – Central – Wan Chai Bypass at WanChai East |
DP3, DP5 |
5 July 2010 |
DP1 |
26 April 2011 |
||
HY/2009/11 |
Wan Chai Development Phase
II and Central – Wan Chai Bypass – North Point Reclamation |
DP3 |
17 March 2010 (Completed) |
HY/2009/15 |
Central-Wanchai Bypass –
Tunnel (Causeway Bay Typhoon Shelter Section) |
DP3 |
10 November 2010 |
DP1 |
13 July 2011 |
||
HK/2010/06 |
Wan Chai Development Phase
II-Central-Wan Chai Bypass over MTR Tsuen Wan Line |
DP3 |
22 March 2011 (Completed) |
04/HY/2006 |
Reconstruction of Bus
Terminus near Man Yiu Street and Man Kwong Street |
DP1 |
September
2010 (Completed) |
HY/2009/17 |
Central – Wan Chai Bypass
(CWB) at FEHD Whitfield Depot – Advanced piling works. |
DP1 |
5
October 2010 (Completed) |
HY/2009/18 |
Central – Wan Chai Bypass
(CWB) – Central Interchange |
DP1 |
21
April 2011 |
HY/2009/19 |
Central – Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2012/08 |
Wan Chai Development Phase II Central- Wan Chai Bypass at Wan Chai West |
DP1,DP2, DP3 |
10 March 2014 |
HY/2010/08 |
Central- Wanchai Bypass
Tunnel – Tunnel (Slip Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
HY/2011/08 |
Central-Wan Chai Bypass
(CWB) – Tunnel Buildings, Systems and Fittings, and Works Associated with
Tunnel Commissioning |
DP1 |
8 October 2014 |
2.4.1.
Civil Engineering and Development Department
and Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the
construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The proposed project organization and lines
of communication with respect to environmental protection works are shown in Figure 2.2. Key personnel and
contact particulars are summarized in Table 2.3:
Table 2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer’s Representative
for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer’s Representative
for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3912 3388 |
3912 3010 |
|
Chun Wo – Leader Joint
Venture |
Contractor under Contract
no. HK/2009/01 |
Project Manager |
Mr. Simon Liu |
9304 8355 |
2587 1878 |
Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction Manager |
Mr. Wyman Wong |
9627 2467 |
|||
Environmental Officer |
Mr. Terry Tsang |
6683 9394 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract
no. HK/2009/02 |
Project Manager |
Mr. Paul Yu |
3658-3085 |
2827 9996 |
Quality & Environmental
Manager |
Mr. C.P. Ho |
9191 8856 |
|||
China State Construction
Engineering (HK) Ltd. |
Contractor under Contract
no. HY/2009/15 |
Project Director |
Chris Leung |
3557 6393 |
2566 2192 |
Senior Site Manager |
Y Huo |
3557 6368 |
|||
Contractor’s Representative |
Rex Lau |
3557 6405 |
|||
Environmental Officer |
Andy Mak |
3557 6347 |
|
||
Chun Wo – CRGL – MBEC Joint Venture |
Contractor under Contract
no. HY/2009/19 |
Project Manager |
Rayland Lee |
3758 6788 |
2570 8013 |
Site
Agent |
David Lau |
3758 8879 |
|||
Deputy Site Agent |
Eric Fong |
6191 9337 |
|||
Environmental Manager / Environmental Officer |
M.H. Isa |
9884 0810 |
|||
|
|
Construction Manager (Marine) |
Andy Chan |
9879 4325 |
|
Construction
Manager (Land) |
Bear Ding |
6483 6198 |
|||
Operation
Manager (Land) |
Yung Kwok Wah |
9834 1010 |
|||
China State- Build King Joint Venture |
Contractor under Contract no. HK/2012/08 |
Project
Director |
C. N. Lai |
9106 5806 |
2877 1522 |
Project
Manager |
Eddie Chung |
9189 8118 |
|||
Site
Agent |
Keith Tse |
9037 1839 |
|||
Environmental
Officer |
James
Ma |
9130 9549 |
|||
Environmental
Supervisor |
Y.
L. Ho |
9856 5669 |
|||
China State |
Contractor under Contract no. HY/2010/08 |
Project
Director |
Chris
Leung |
3467 4299 |
2566 8061 |
|
|
Project
Manager |
Chan
Ying Lun |
3418 3001 |
|
|
|
Site Agent |
Francis Suen |
6672 0311 |
|
|
|
Environmental
Officer |
Gabriel
Wong |
35576466 |
|
|
|
Environmental
Supervisor |
Desmond
Ho Tsz Ho |
3557 6466 |
|
Ramboll
Environ Hong Kong Limited |
Independent Environmental Checker (IEC) |
Independent Environmental
Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader
(ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
For Contract no. HK/2009/01, the principal
work activities in this reporting month included:
Nil
2.4.4.
For Contract no. HK/2009/02, the principal
work activities in this reporting month included:
Nil
2.4.5.
For Contract no. HY/2009/15, the principal
work activities in this reporting month included:
·
Reinstatement of Eastern Breakwater
2.4.6.
For Contract no. HY/2009/19, the principal
work activity in this reporting month included:
Nil
2.4.7.
For Contract no. HK/2012/08, the principal
work activity in this reporting month included:
·
Installation for Box 1 unit
·
Construction of culvert L Bay 8
2.4.8.
For Contract no. HY/2010/08, no principal
work activities this reporting month.
·
Diversion pipe maintenance
·
Preparation for Diaphragm Wall Removal Works
2.4.9.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
Contract no.
HK/2009/01 – Wan Chai Development Phase II – Central –Wanchai Bypass at HKCEC
Nil
Contract no.
HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan
Chai East
·
Nil
Contract no.
HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter
Section)
·
Nil
Contract no.
HY/2009/19- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern
Corridor Link
Nil
Contract no.
HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan
Chai West
·
Construction of Box 1 unit
·
Construction of culvert L Bay 8
Contract no.
HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip Road 8)
·
Diversion pipe maintenance
·
Preparation for Diaphragm Wall Removal Works
3.1.1.
A summary of the current status on licences
and/or permits on environmental protection pertinent to the Project is shown in
Table 3.1.
Table 3.1 Summary
of the current status on licences and/or permits on environmental protection
pertinent to the Project
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Superseded |
Environmental Permit |
EP-364/2009/B |
20 Sep 2012 |
Superseded |
Environmental Permit |
EP-364/2009/C |
11 Jul 2014 |
Superseded |
Environmental Permit |
EP-364/2009/D |
24 Nov 2016 |
Superseded |
Environmental Permit |
EP-364/2009/E |
22 Dec 2016 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-04/356/2009 |
22 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Surrendered |
Further Environmental Permit |
FEP-01/364/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-02/364/2009 |
21 Apr
2010 |
Valid |
Further Environmental Permit |
FEP-03/364/2009 |
12 Jul
2010 |
Surrendered |
Further Environmental Permit |
FEP-04/364/2009/A |
14 Oct
2010 |
Surrendered |
Further Environmental Permit |
FEP-05/364/2009/A |
15 Nov
2010 |
Valid |
Further Environmental Permit |
FEP-06/364/2009/A |
22 Nov
2010 |
Valid |
Further Environmental Permit |
FEP-07/364/2009/B |
20 Sep
2012 |
Surrendered |
Further Environmental Permit |
FEP-07/364/2009/D |
24 Nov
2015 |
Valid |
Further Environmental Permit |
FEP-08/364/2009/A |
15 Jun
2012 |
Surrendered |
Further Environmental Permit |
FEP-06/356/2009 |
5 Mar 2013 |
Valid |
Further Environmental Permit |
FEP-07/356/2009 |
26 July 2013 |
Valid |
Further Environmental Permit |
FEP-09/364/2009/B |
5 March 2013 |
Valid |
Further Environmental Permit |
FEP-10/364/2009/B |
26 July 2013 |
Valid |
Further Environmental Permit |
FEP-11/364/2009/B |
2 May 2014 |
Superseded |
Further Environmental Permit |
FEP-08/356/2009 |
1 Aug 2016 |
Valid |
Further Environmental Permit |
FEP-11/364/2009/E |
22 Dec 2016 |
Valid |
3.1.2.
Due to the multi-contract nature of the
Project, the status of permits and/or licences under the individual contract(s)
are presented as below:
Contract no. HK/2010/06 – Wan Chai
Development Phase II – Central – Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-05/356/2009
3.1.3.
The construction works were completed and the
FEP-05/356/2009 was surrendered by the Contractor on 3 October 2014.
Contract no.
HK/2009/01 – Wan Chai Development Phase II – Central –Wanchai Bypass at HKCEC
3.1.4.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission for
contract no. HK/2009/01 under FEP-02/356/2009 are shown in Table 3.2 and
Table 3.3.
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Permits
and/or Licences |
Reference
No. |
Issued Date
|
Valid Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313088 |
06 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS1004-16 |
28 Sep 2016 |
29 Sep 2016 to 27 Mar 2017 |
Valid |
GW-RS1079-16 |
27 Oct 2016 |
27 Oct 2016 to 20 Apr 2017 |
Valid |
|
|
GW-RS1241-16 |
12 Dec 2016 |
15 Dec 2016 to 6 Jun 2017 |
Valid |
|
GW-RS1240-16 |
12 Dec 2016 |
13 Dec 2016 to 6 Jun 2017 |
Valid |
|
GW-RS1233-16 |
12 Dec 2016 |
14 Dec 2016 to 6 Jun 2017 |
Valid |
|
GW-RS1234-16 |
12 Dec 2016 |
20 Dec 2016 to 19 Jun 2017 |
Valid |
Discharge
Licence |
WT00024952-2016 |
6 Jul 2016 |
31 Jul 2021 |
Valid |
|
WT00024844-2016 |
29 Jun 2016 |
31 Mar 2020 |
Valid |
Billing
account under Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration
as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Table 3.3 Summary
of submission status under FEP-02/356/2009 Condition
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of
Main Construction Companies |
13 Apr 2010 |
Condition 2.7 |
Works Schedule and Location Plan |
8 Apr 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan (Rev. 5) |
24 Aug 2012 |
Silt Curtain Deployment Plan (Rev. 4) |
12 July 2012 |
|
Silt Curtain Deployment Plan (Rev. 3) |
27 June 2012 |
|
Silt Curtain Deployment Plan |
19 Apr 2010 |
|
Condition 2.9 |
Silt Screen Deployment Plan (Rev. 9) |
5 Nov 2015 |
Silt Screen Deployment Plan (Rev. 8) |
7 Sep 2015 |
|
Silt Screen Deployment Plan (Rev. 7) |
21 Nov 2014 |
|
Silt Screen Deployment Plan (Rev. 6) |
20 Aug 2014 |
|
Silt Screen Deployment Plan (Rev.5) |
24 Jul 2013 |
|
Silt Screen Deployment Plan (Rev.4) |
15 Nov 2012 |
|
Silt Screen Deployment Plan |
19 Apr 2010 |
|
Conditions 2.8 and 2.9 |
Supplementary Document on Silt Curtain and Silt Screen Deployment Plan |
19 Jul 2010 |
Report on Field Testing for Silt Curtain |
26 Aug 2010 |
|
Report on Field Testing for Silt Curtain (Rev. A) |
15 Nov 2010 |
|
Condition 2.12(d) |
Alternative Proposal on Concurrent Dredging for Sewage Pipeline and
Cross Harbour Water Mains |
15 Apr 2011 |
Condition 2.17 |
Noise Management Plan |
23 Apr 2010 |
Condition 2.18 |
Landscape Plan (Erection of Decorative Screen Hoarding along
Construction Site around Hong Kong Exhibition and Convention Centre) |
15 May 2010 |
|
Landscape Plan (Night-time Lighting) |
22 Oct 2010 |
|
Landscape Plan (Rev. B) |
15 Nov 2010 |
Condition 1.12 |
Notification of Commencement Date |
20 Jun 2011 |
Condition 2.6 to 2.8 |
Management Organization, Works Schedule and Location Plan |
18 May 2011 |
Condition 2.9 |
Silt Screen Deployment Plan |
10 Jun 2011 |
Condition 2.18 |
Landscape Plan |
31 Oct 2013 |
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at WanChai East
3.1.5.
Summary of the current status on licences and/or permits on
environmental protection pertinent and submission for contract no. HK/2009/02
under FEP-03/356/2009 are shown in Table 3.4 and Table 3.5.
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Permits
and/or Licences |
Reference
No. |
Issued Date
|
Valid Period/ Expiry Date |
Status |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
|
|
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
Notification
of Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for
non-piling equipment |
GW-RS1047-16 |
13 Oct 2016 |
26 Oct 2016 to 25
Apr 2017 |
Valid |
GW-RS1140-16 |
11 Nov 2016 |
14 Nov 2016 to 9
May 2017 |
Valid |
|
GW-RS1297-16 |
15 Dec 2016 |
16 Dec 2016 to 14
Jun 2017 |
Valid |
|
GW-RS1305-16 |
22 Dec 2016 |
24 Dec 2016 to 13
Jun 2017 |
Valid |
|
Discharge Licence |
WT00022295-2015 |
12 Aug 2015 |
31 July 2020 |
Valid |
|
WT00025276-2016 |
19 Sep 2016 |
31 July 2021 |
Valid |
Billing Account under Waste Disposal
Ordinance (Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance
(Marine) |
7011496 |
6 Oct 2010 |
N/A |
Valid |
Registration as Chemical Waste Producer
(Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Registration as Chemical Waste Producer
(TKO 137) |
WPN5213-839-C3593-02 |
22 Sep 2010 |
N/A |
Valid |
Table 3.5 Summary of submission status under
FEP-03/356/2009 Condition
EP Condition |
Submission |
Date of Submission |
Condition 1.12 |
Commencement Date of Construction of Marine Works |
8 April 2010 |
Condition 2.6 |
Management Organization of Main Construction Companies |
10 April 2010 |
Condition 2.7 |
Works Schedule and Location Plans |
8 April 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan (Revision A) |
20 April
2010 |
Silt Curtain Deployment Plan (Revision B) |
25 May
2010 |
|
Silt Curtain Deployment Plan (Revision C) |
14 Jun
2010 |
|
Silt Curtain Deployment Plan (Revision H) |
15 Feb
2011 |
|
Silt Curtain Deployment Plan (Revision I) |
17 Nov
2011 |
|
Silt Curtain Deployment Plan (Revision J) |
15 Feb
2012 |
|
Silt Curtain Deployment Plan (Revision K) |
3 May 2012 |
|
Silt Curtain Deployment Plan (Revision L) |
25 Oct
2012 |
|
Silt Curtain Deployment Plan (Revision M) |
30 Nov 2012 |
|
Condition 2.9 |
Silt Screen Deployment Plan |
21 April
2010 |
Supplementary Information for Existing WSD Salt Water Intakes at
Quarry Bay and Sai Wan Ho |
5 Oct 2010 |
|
Silt Screen Deployment Plan (Revision B) |
15 Feb 2012 |
|
Silt Screen Deployment Plan (Revision C) |
3 May 2012 |
|
Silt Screen Deployment Plan (Revision D) |
10 Dec 2012 |
|
|
Silt Screen Deployment Plan (Revision E) |
6 May 2013 |
|
Silt Screen Deployment Plan (Revision F) |
23 Nov 2016 |
Condition 2.17 |
Noise Management Plan |
6 May 2010 |
Condition 2.18 |
Landscape Plan (Decorative Screen Hoarding) |
11 May
2010 |
Landscape Plan (Control of Night Time Lighting) |
2 June
2010 |
|
Landscape Plan (Combined Version) |
20 July
2011 |
|
Landscape Plan (Combined Version) |
5 Aug 2011 |
|
----- |
Acknowledge of Submission |
22 Aug
2011 |
Contract no. HY/2009/15 – Central-Wanchai
Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)
3.1.6.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission for
contract no. HY/2009/15 under FEP-04/356/2009 are shown in Table 3.6 and
Table 3.7.
Table 3.6 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/15
Permits
and/or Licences |
Reference
No. |
Issued Date
|
Valid Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-04/356/2009 |
22 Nov 2010 |
N/A |
Valid |
Notification
of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for concreting works at Eastern
Breakwater of CBTS |
GW-RS0889-16 |
23 Aug 2016 |
11 Sep 2016 to 10 Mar 2017 |
Valid |
Construction Noise Permit (CNP) for
reclamation and d-wall works at Ex-PCWA |
GW-RS0884-16 |
23 Aug 2016 |
8 Sep 2016 to 7 Mar 2017 |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Billing
Account under Waste Disposal Ordinance |
7011553 |
30 Sep 2010 |
N/A |
Valid |
Billing
Account under Waste Disposal Ordinance (Disposal by Vessel) |
7011761 |
30 Dec 2016 |
17 Jan 2017
to 16 Apr 2017 |
Valid |
Table 3.7 Summary
of submission status under FEP-04/356/2009 Condition
FEP
Condition |
Submission |
Date of
Submission |
Condition
2.6 |
Management
Organization of Main Construction Companies |
30 Sep 2010 |
Amendment
for Management Organization of Main Construction Companies |
16 May 2011 |
|
Condition
2.7 |
Works
Schedule and Location Plans |
27 Oct 2010 |
|
Amendment
for Works Schedule and Location Plans |
12 Nov 2010 |
Condition
2.8 |
Silt Curtain
Deployment Plan |
30 Nov 2010 |
|
Amendment
for Silt Curtain Deployment Plan |
24 Feb 2011 |
Amendment
for Silt Curtain Deployment Plan |
11 May 2011 |
|
Amendment
for Silt Curtain Deployment Plan |
11 Sep 2012 |
|
Amendment
for Silt Curtain Deployment Plan |
30 Oct 2012 |
|
Condition
2.9 |
Silt Screen Deployment Plan |
19 Oct 2010 |
Amendment
for Silt Screen Deployment Plan |
18 Feb 2011 |
|
Amendment
for Silt Screen Deployment Plan |
15 Jun 2011 |
|
Condition
2.18 |
Proposal for the Removal of Odorous Sediment and Slime |
13 Jan 2011 |
Amendment
for Proposal for the Removal of Odorous Sediment and Slime |
8 Mar 2011 |
|
|
Amendment
for Proposal for the Removal of Odorous Sediment and Slime |
2 Aug 2011 |
Condition
2.21 |
Landscape
Plan |
18 Feb 2011 |
Condition
2.23 |
Noise Management
Plan |
20 Oct 2010 |
Amendment
for Noise Management Plan |
27 Jan 2011 |
Contract no. HY/2009/19 – Central- Wan Chai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
3.1.7.
Summary of the current status on licences
and/or permits on environmental protection pertinent for contract no. HY/2009/19
is shown in Table 3.8
Table 3.8 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/19
Permit /
Licence / Notification / Approval |
Reference
No. |
Issued Date |
Valid
Period / Expiry date |
Status |
Further
Environmental Permit |
FEP-07/364/2009/D |
24 Nov 2015 |
Granted |
Valid |
Notification
of Works Under APCO |
326160 |
24 Jan 2011 |
Notified |
Valid |
Construction Noise Permit (CNP) (For Portion Vi Marine) |
GW-RS1251-16 |
7 Dec 2016 |
18 Dec 2016 to 17 Jun 2017 |
Valid |
C&D Waste Disposal |
7012306 |
10 Feb 2011 |
Registered |
- |
Vessel Disposal |
7013285 |
21 July 2011 |
Registered |
- |
Registration as Chemical Waste Producer |
5213-151-C3654-01 |
24 Mar 2011 |
Registered |
- |
Contract no.
HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan
Chai West
3.1.8.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission for
contract no. HK/2012/08 under FEP-08/356/2009 are shown in Table 3.9 and Table 3.10.
Table 3.9 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2012/08
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-06/356/2009 |
5 Mar 2013 |
N/A |
Valid |
|
FEP-08/356/2009 |
1 Aug 2016 |
N/A |
Valid |
Notification of Works Under
APCO |
355439 |
4 Feb 2013 |
N/A |
Valid |
Registration as a Chemical
Waste Producer |
5213-134-C3790-01 |
30 Jun 2016 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance |
7016883 |
18 Feb 2013 |
18 Jul 2017 |
Valid |
Water Discharge Licence |
WT00020594-2014 |
22 Dec 2014 |
31 Jan 2019 |
Valid |
Construction Noise Permit |
GW-RS0902-16 |
24 Aug 2016 |
26 Aug 2016 to 25 Feb 2017 |
Expired |
|
GW-RS1076-16 |
14 Oct 2016 |
17 Oct 2016 to 31 Jan 2017 |
Expired |
|
GW-RS1335-16 |
29 Dec 2016 |
13 Jan 2017 to 12 Jul 2017 |
Valid |
|
GW-RS1340-16 |
23 Dec 2016 |
13 Jan 2017 to 12 Jul 2017 |
Valid |
|
GW-RS1336-16 |
29 Dec 2016 |
13 Jan 2017 to 12 Jul 2017 |
Valid |
|
GW-RS1349-16 |
23 Dec 2016 |
13 Jan 2017 to 12 Jul 2017 |
Valid |
|
GW-RS0098-17 |
1 Feb 2017 |
26 Feb 2017 to 25 Aug 2017 |
Valid |
Dumping Permit (Type 1 –
Open Sea Disposal) |
EP/MD/17-160 |
6 Feb 2017 |
8 Feb 2017 to 30 Jun 2017 |
Valid |
Table 3.10 Summary
of submission status under EP-356/2009 and FEP-06/356/2009 Condition
FEP Condition |
Submission |
Date of Submission |
Condition 2.8 |
Silt Curtain Deployment Plan
(Rev. 3) |
Submitted on 25 Nov 2013 was returned to CSLJV by
EPD. |
Condition 2.9 |
Silt Screen Deployment Plan
(Rev. 2) |
Generally in order as commented by EPD on 19 Sep
2013 |
Condition 2.23 |
Noise Management Plan (Rev.
2) |
Generally in order as
commented by EPD on 15 Aug 2013 |
Condition 2.24 |
Landscape Plan (Rev. 3) |
Generally in order as commented by EPD on 31 Oct
2013 |
Contract no. HY/2010/08
–Central - Wan Chai Bypass (CWB) –Tunnel (Slip Road 8)
3.1.9.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission for
contract no. HY/2010/08 under FEP-07/356/2009 are shown in Table 3.11
and Table
3.12.
Table 3.11 Cumulative Summary of
Valid Licences and Permits under Contract no. HY/2010/08
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-07/356/2009 |
26 Jul 2013 |
NA |
Valid |
|
FEP-10/364/2009/B |
26 Jul 2013 |
NA |
Valid |
Notification of Works Under
APCO |
357176 |
2 Apr 2013 |
NIL |
Valid |
Registration as a Chemical
Waste Producer |
WPN5213-147-C1169-44 |
27 Mar 2013 |
NIL |
Valid |
Billing Account under Waste
Disposal Ordinance |
7017170 |
27 Mar 2013 |
NIL |
Valid |
Billing Account under Waste Disposal Ordinance (Dumping
by Vessel) |
7020947 |
22 Dec 2014 |
NIL |
Valid. |
Water Discharge Licence |
WT00020753-2015 |
3 Feb 2015 |
28 Feb 2017 |
Valid |
Construction Noise Permit |
GW-RW-0562-16 |
28 Oct 2016 |
28 Oct 2016 to 26 Apr 2017 |
Valid |
Table 3.12 Summary
of submission status under EP-356/2009 and FEP-07/356/2009 Condition
FEP Condition |
Submission |
Date of Submission |
Condition 2.8 |
Silt Curtain Deployment Plan
(rev03) |
24 Dec 2014 |
Condition 2.9 |
Silt Screen Deployment Plan (rev02) |
18 Feb 2015 |
Condition 2.23 |
Noise Management Plan
(rev02) |
25 Mar 2014 |
Condition 2.24 |
Landscape Plant (rev04) |
23
Sep 2014 |
Noise Monitoring Stations
4.1.1.
The noise monitoring stations for the Project
are listed and shown in Table 4.1 and Figure 4.1.
Appendix 4.1 shows
the established Action/Limit Levels for the monitoring works.
Table 4.1 Noise Monitoring Station
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
City
Garden |
M6 |
HK Baptist Church Henrietta Secondary School |
Noise Monitoring Parameters, Frequency and Duration
4.1.2.
The construction
noise level shall be measured in terms of the A-weighted equivalent continuous
sound pressure level (Leq). Leq (30 minutes) shall be
used as the monitoring parameter for the time period between 0700 and 1900
hours on normal weekdays. For all other time periods, Leq (5 minutes)
shall be employed for comparison with the Noise Control Ordinance (NCO)
criteria. Supplementary information for data auditing,
statistical results such as L10 and L90 shall also be obtained for reference.
4.1.3.
Noise monitoring shall be carried out at all
the designated monitoring stations. The monitoring frequency shall depend on
the scale of the construction activities. The following is an initial guide on
the regular monitoring frequency for each station on a weekly basis when noise
generating activities are underway:
·
One set of measurements between 0700 and 1900
hours on normal weekdays.
4.1.4.
If construction works are extended to include
works during the hours of 1900 – 0700 as well as public holidays and Sundays,
additional weekly impact monitoring shall be carried out during respective
restricted hours periods. Applicable permits under NCO shall be obtained by the
Contractor.
Monitoring Equipment
4.1.5.
As referred to in the Technical Memorandum ™
issued under the NCO, sound level meters in compliance with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications shall be used for carrying out the noise monitoring.
Immediately prior to and following each noise measurement the accuracy of the
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency. Measurements may be accepted
as valid only if the calibration level from before and after the noise
measurement agree to within 1.0 dB.
4.1.6.
Noise measurements shall not be made in fog,
rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10
m/s. The wind speed shall be checked with a portable wind speed meter capable
of measuring the wind speed in m/s.
Air Quality Monitoring Stations
4.2.1.
The air monitoring stations for the Project
are listed and shown in Table 4.2 and Figure 4.1.
Appendix 4.1 shows
the established Action/Limit Levels for the monitoring works.
Table 4.2 Air
Monitoring Station
Station ID |
Monitoring Location |
Description |
CMA1b |
Oil Street Site Office** |
North Point |
CMA2a |
Causeway Bay Community Centre |
Causeway Bay |
CMA3a |
CWB PRE Site Office * |
Causeway Bay |
CMA4a |
Society for the Prevention of Cruelty to Animals |
Wan Chai |
CMA5b |
Pedestrian Plaza*** |
Wan Chai |
CMA6a |
WDII PRE Site Office * |
Wan Chai |
Remarks*: As per
the ENPC meeting in March 2011, the monitoring stations CMA3a – Future CWB site
office at Wanchai Waterfront Promenade was renamed as remark.
Remarks**: The
location ID of monitoring station CMA1b was updated as “Oil Street Site Office”
in April 2013.
Remarks***: The
station ID and monitoring location was updated in December 2014 with respect to
monitoring station relocation.
Air Monitoring Parameters, Frequency and Duration
4.2.2.
One-hour and 24-hour TSP levels should be
measured to indicate the impacts of construction dust on air quality. The
24-hour TSP levels shall be measured by following the standard high volume
sampling method as set out in the Title 40 of the Code of Federal Regulations,
Chapter 1 (Part 50), Appendix B.
4.2.3.
All relevant data including temperature,
pressure, weather conditions, elapsed-time meter reading for the start and stop
of the sampler, identification and weight of the filter paper, and any other
local atmospheric factors affecting or affected by site conditions, etc., shall
be recorded down in detail.
4.2.4.
For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and Monitoring Equipment
4.2.5.
High volume samplers (HVSs) in compliance
with the following specifications shall be used for carrying out the 1-hour and
24-hour TSP monitoring:
·
0.6 – 1.7 m3 per minute adjustable flow
range;
·
equipped with a timing / control device with
+/- 5 minutes accuracy for 24 hours operation;
·
installed with elapsed-time meter with +/- 2
minutes accuracy for 24 hours operation;
·
capable of providing a minimum exposed area
of 406 cm2;
·
flow control accuracy: +/- 2.5% deviation
over 24-hour sampling period;
·
equipped with a shelter to protect the filter
and sampler;
·
incorporated with an electronic mass flow
rate controller or other equivalent devices;
·
equipped with a flow recorder for continuous
monitoring;
·
provided with a peaked roof inlet;
·
incorporated with a manometer;
·
able to hold and seal the filter paper to the
sampler housing at horizontal position;
·
easily changeable filter; and
·
capable of operating continuously for a
24-hour period.
4.2.6.
Initial calibration of dust monitoring
equipment shall be conducted upon installation and thereafter at bi-monthly
intervals. The transfer standard shall be traceable to the internationally
recognized primary standard and be calibrated annually. The concern parties
such as IEC shall properly document the calibration data for future reference.
All the data should be converted into standard temperature and pressure
condition.
Laboratory Measurement / Analysis
4.2.7.
A clean laboratory with constant temperature
and humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
4.2.8.
An alternative non-HOKLAS
accredited laboratory was set-up for carrying
out the laboratory analysis, the laboratory equipment was approved by
the ER on 8 February 2011 and the measurement
procedures were witnessed by the IEC. Any measurement
performed by the laboratory was be
demonstrated to the satisfaction of the ER and IEC. IEC shall regularly audit
to the measurement performed by the laboratory to ensure the accuracy of
measurement results.
4.2.9.
Filter paper of size 8” x 10” shall be
labelled before sampling. It shall be a clean filter paper with no pinholes,
and shall be conditioned in a humidity-controlled chamber for over 24-hours and
be pre-weighed before use for the sampling.
4.2.10.
After sampling, the filter paper loaded with
dust shall be kept in a clean and tightly sealed plastic bag. The filter paper
shall then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
4.2.11.
All the collected samples shall be kept in a
good condition for 6 months before disposal.
impact monitoring for odour patrol
4.2.12.
Odour patrols along the shorelines of
Causeway Bay Typhoon Shelter and ex-Wan Chai Public Cargo Working Area when
there is temporary reclamation in Causeway Bay Typhoon Shelter and/or in the
ex-Wan Chai Public Cargo Working Area, or when there is dredging of the odorous
sediment and slime at the south-western corner of the Causeway Bay Typhoon
Shelter. Odour patrols will be carried out at bi-weekly intervals during July,
August and September by a qualified person of the ET who shall:
·
be at least 16 years of age;
·
be free from any respiratory illnesses; and
·
not be allowed to smoke, eat, drink (except
water) or use chewing gum or sweets 30 min
·
before and during odour patrol
4.2.13.
Odour patrol shall be conducted by
independent trained personnel / competent persons patrolling and sniffing
around the shore as shown in Figure 4.1
to detect any odour at the concerned hours (afternoon is preferred for higher
daily temperature).
4.2.14.
The qualified person will use the nose
(olfactory sensor) to sniff odours at different locations. The main odour
emission sources and the areas to be affected by the odour nuisance will be identified.
4.2.15.
The perceived odour intensity is to be
divided into 5 levels which are ranked in the descending order as follows:
·
0 – Not detected. No odour perceived or an
odour so weak that it cannot be easily characterized or described;
·
1 – Slight Identifiable odour, and slight
chance to have odour nuisance;
·
2 – Moderate Identifiable odour, and moderate
chance to have odour nuisance;
·
3 – Strong Identifiable, likely to have odour
nuisance;
·
4 – Extreme Severe odour, and unacceptable
odour level.
4.2.16.
The findings including odour intensity, odour
nature and possible odour sources, and also the local wind speed and direction
at each location will be recorded. In addition, some relevant meteorological
and tidal data such as daily average temperature, and daily average humidity,
on that surveyed day will be obtained from the Hong Kong Observatory Station
for reference. The Action and Limit levels for odour patrol are shown in Appendix 4.1.
4.2.17.
The qualified odour patrol member has
individual n-butanol thresholds complied with the requirement of European Standard
Method of Air Quality – Determination of Odour Concentration by Dynamic
Olfactometry (EN13725) in the range of 20 to 80 ppb.
4.3.1.
The EIA Report has identified that the key
water quality impact would be associated with the dredging works during the
construction phase. Marine water quality monitoring for dissolved oxygen (DO),
suspended solid (SS) and turbidity is therefore recommended to be carried out
at selected WSD flushing water intakes. The impact monitoring should be carried
out during the proposed dredging works to ensure the compliance with the water
quality standards.
4.3.2.
The updated EM&A Manual for EP-356/2009
(Version in March 2011) is approval by EPD on 29 April 2011. As such, the
Action Level and Limit Level for the wet season (April – September) will be
effected and applied to the water quality monitoring data from 30 April 2011.
Water Quality
Monitoring Stations
4.3.3.
Water quality monitoring was undertaken at 8
monitoring stations for WSD salt water intakes and cooling water intakes along
the seafront of the Victoria Harbour in the reporting month. The proposed water
quality monitoring stations of the Project are shown in Table 4.3 and
Figure 4.1. Appendix 4.1 shows
the established Action/Limit Levels for the monitoring works.
Table 4.3 Marine Water Quality
Stations for Water Quality Monitoring
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
Cooling Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
C7 |
Windsor House |
837193.7 |
816150.0 |
P1 |
HKCEC Phase I |
835774.7 |
816179.4 |
P3 |
The Academy of performing
Arts |
835824.6 |
816212.0 |
P4 |
Shui on Centre |
835865.6 |
816220.0 |
P5 |
Government Buildings (Wanchai Tower / Revenue Tower /
Immigration Tower) |
835895.2 |
816215.2 |
Cooling Water
Intake / WSD Salt Water Intake |
|||
RW21-P789 |
Great Eagle Centre/ Sun
Hung Kai Centre/ WSD Wanchai salt water intake / China Resources Building |
836268.0 |
816020.0 |
Remarks: - The cessation of seawater
intake operation for C6 was confirmed on 17 May 2011 and the water quality monitoring
at C6 was then terminated since 17 May 2011.
- 4-week post construction water quality
monitoring at WSD9, WSD10, WSD15 and WSD17 were completed on 6 Feb 2012 and the
water quality monitoring at WSD 10 and WSD15 were temporary suspended since 8
Feb 2012, and WSD9 and WSD17 was implemented with respect to HK/2009/02 from 8
Feb 2012 onwards.
- C8 and C9 were implemented with
respect to HY/2009/19 from 28 Jan 2012.
- C8 & C9
were temporary suspended since 4 March 2013.
- WSD7 and WSD20 water quality
monitoring were temporarily suspended from 27 Apr 2012.
-
C2, C3 C4e and
C4w water quality monitoring station was temporarily suspended since 22 Apr
2013
-
P1, P3, P4 and P5
were commenced since 24 Apr 2013
- C5e and C5w
water quality monitoring station was temporarily suspended since 29 Jul 2013.
- WSD21 water
quality monitoring station was temporarily suspended since 12 Mar 2014
- WSD9 and
WSD17 water quality monitoring station was temporarily suspended since 8 Sep
2014 flood tide.
- The water quality monitoring station
C1 shall be associated with Contract No. HK/2009/02 upon commencement of marine
works under DP3 at WCR3 area.
- The water quality monitoring station RW21-P789
was adjusted to RW21-P789E and RW21-P789W since 28 November 2016 ebb-tide.
- The water quality monitoring was
reverted to previous monitoring station RW21-P789 from PW21-P789E and
RW21-P789W from 25 January 2017 onwards.
Water Quality Parameters
4.3.4.
Monitoring of dissolved oxygen (DO),
turbidity and suspended solids (SS) shall be carried out at WSD flushing water
intakes and cooling water intakes. DO and Turbidity are measured in-situ while
SS is determined in laboratory.
4.3.5.
In association with the water quality
parameters, other relevant data shall also be measured, such as monitoring
location/position, time, sampling depth, water temperature, pH, salinity, dissolved
oxygen (DO) saturation, weather conditions, sea conditions, tidal stage, and
any special phenomena and work underway at the construction site etc.
Sampling Procedures and Monitoring Equipment
4.3.6.
The interval between two sets of monitoring
should not be less than 36 hours except where there are exceedances of Action
and/or Limit Levels, in which case the monitoring frequency will be increased. Table
4.4 shows the proposed monitoring frequency and water quality
parameters. Duplicate in-situ measurements and water sampling should be carried
out in each sampling event. For selection of tides for in-situ measurement and
water sampling, tidal range of individual flood and ebb tides should be not
less than 0.5m.
Table 4.4 Marine Water Quality Monitoring Frequency and
Parameters
Activities |
Monitoring Frequency1 |
Parameters2 |
During the 4-week baseline monitoring period |
Three days per week, at mid-flood and mid-ebb tides |
Turbidity, Suspended Solids (SS), Dissolved Oxygen (DO), pH,
Temperature, Salinity |
During marine construction works |
Three days per week, at mid-flood and mid-ebb tides |
Turbidity, Suspended Solids (SS), Dissolved Oxygen (DO), pH,
Temperature, Salinity |
After completion of marine construction
works |
Three days per week, at mid-flood and mid-ebb tides |
Turbidity, Suspended Solids (SS), Dissolved Oxygen (DO), pH,
Temperature, Salinity |
Notes:
1. For selection of tides for in-situ measurement and water
sampling, tidal range of individual flood and ebb tides should be not less than
0.5m.
2.
Turbidity
should be measured in situ whereas SS should be determined by laboratory.
Dissolved Oxygen and Temperature Measuring Equipment
4.3.7.
The instrument should be a portable,
weatherproof dissolved oxygen measuring instrument complete with cable, sensor,
comprehensive operation manuals, and use a DC power source. It should be
capable of measuring:
·
a dissolved oxygen level in the range of 0-20
mg/l and 0-200% saturation
·
a temperature of 0-45 degree Celsius
4.3.8.
It should have a membrane electrode with
automatic temperature compensation complete with a cable. Sufficient stocks of
spare electrodes and cables should be available for replacement where
necessary. (e.g. YSI model 59 meter, YSI 5739 probe, YSI 5795A submersible
stirrer with reel and cable or an approved similar instrument).
4.3.9.
Should salinity compensation not be build-in
in the DO equipment, in-situ salinity shall be measured to calibrate the DO
equipment prior to each DO measurement.
Turbidity Measurement Instrument
4.3.10.
The instrument should be a portable,
weatherproof turbidity-measuring instrument complete with comprehensive
operation manual. The equipment should use a DC power source. It should have a
photoelectric sensor capable of measuring turbidity between 0‑1000 NTU and be
complete with a cable (e.g. Hach model 2100P or an approved similar
instrument).
Sampler
4.3.11.
A water sampler comprises a transparent PVC
cylinder, with a capacity of not less than 2 litres, and can be effectively
sealed with latex cups at both ends. The sampler should have a positive
latching system to keep it open and prevent premature closure until released by
a messenger when the sampler is at the selected water depth (e.g. Kahlsico
Water Sampler or an approved similar instrument).
Sample Container and Storage
4.3.12.
Water samples for suspended solids
measurement should be collected in high-density polythene bottles, packed in
ice (cooled to 4°C without being frozen), and delivered to ALS Technichem (HK)
Pty Ltd. as soon as possible after collection for analysis.
Water Depth Detector
4.3.13.
A portable, battery-operated echo sounder
shall be used for the determination of water depth at each designated
monitoring station. This unit can either be handheld or affixed to the bottom
of the workboat, if the same vessel is to be used throughout the monitoring
programme.
Salinity
4.3.14.
A portable salinometer capable of measuring
salinity in the range of 0-40 ppt shall be provided for measuring salinity of
the water at each of monitoring location.
Monitoring Position Equipment
4.3.15.
A hand-held or boat-fixed type digital Global
Positioning System (GPS) with waypoint bearing indication or other equivalent
instrument of similar accuracy shall be provided and used during monitoring to
ensure the monitoring vessel is at the correct location before taking
measurements.
Calibration of In-situ Instruments
4.3.16.
All in-situ monitoring instrument shall be
checked, calibrated and certified by a laboratory accredited under HOKLAS or
equivalent before use, and subsequently re-calibrated at 3 monthly intervals
throughout all stages of the water quality monitoring. Responses of sensors and
electrodes should be checked with certified standard solutions before each use.
Wet bulb calibration for a DO meter shall be carried out before measurement at
each monitoring location.
4.3.17.
For the on site calibration of field
equipment by the ET, the BS 127:1993, "Guide to Field and on-site test
methods for the analysis of waters" should be observed.
4.3.18.
Sufficient stocks of spare parts should be
maintained for replacements when necessary. Backup monitoring equipment shall
also be made available so that monitoring can proceed uninterrupted even when
some equipment is under maintenance, calibration, etc.
4.3.19.
Current calibration certificates of
equipments are presented in Appendix 4.2.
Laboratory Measurement / Analysis
4.3.20.
Analysis of suspended solids has been carried
out in a HOKLAS accredited laboratory, ALS Technichem (HK) Pty Ltd. Water
samples of about 1L shall be collected at the monitoring stations for carrying
out the laboratory SS determination. The SS determination work shall start
within 24 hours after collection of the water samples. The SS determination
shall follow APHA 19ed or equivalent methods subject to the approval of IEC and
EPD.
Enhanced Water Quality Monitoring in the ex-Wan Chai Public Cargo
Working Area and the Causeway Bay Typhoon Shelter
4.3.21.
The enhanced water quality monitoring and
audit programme is to avoid aggravation of odour nuisance from seawater arising
from temporary reclamation in the ex-Wan Chai Public Cargo Working Area and the
Causeway Bay Typhoon Shelter.
4.3.22.
Dissolved oxygen monitoring at the intakes C6
and C7 in Causeway Bay Typhoon Shelter when there is temporary reclamation in
Causeway Bay Typhoon Shelter and at the south-western and south-eastern corners
of the ex-Wan Chai Public Cargo Working Area. The proposed water quality
monitoring stations of the Project are shown in Table 4.5 and Figure 4.1.
Table 4.5 Marine Water Quality
Stations for Enhanced Water Quality Monitoring
Station |
Location |
C6 |
Excelsior Hotel |
C7 |
Windsor
House |
Ex-WPCWA-SW |
South-western of the ex-Wan Chai Public Cargo Working Area |
Ex-WPCWA-SE |
South-eastern of the ex-Wan Chai Public Cargo Working Area |
Remarks:
1.
Enhanced DO monitoring at Windsor House Cooling (Station Ref: C7) was
temporarily suspended since 22 October 2014 with respect to the formation of
temporary reclamation zone TS3 and to be resumed upon removal of the respective
temporary reclamation zone.
2. Enhanced
DO monitoring at Monitoring station Ex-WPCWA SE was temporarily suspended from
31 August 2015 with respect to seawall reinstatement works and formation of
active works area. The Enhance DO monitoring at Ex-WPCWA SE was resumed on 11
May 2016 due to completed section of seawall reinstatement works at Ex-PCWA.
4.3.23.
The monitoring of dissolved oxygen are to be
carried out 3 days per week, at mid-flood and mid-ebb tides for 3 water depths
(1m below water surface, mid-depth and 1m above sea bed, except where the water
depth less than 6m, the mid-depth may be omitted. If the water depth be equal
to or less than 3m, only the mid-depth will be monitored).
Daily SS Monitoring and 24 hours Turbidity Monitoring System
4.3.24. During dredging of
the sediment at the south-western corner of the Causeway Bay Typhoon Shelter, daily monitoring of suspended solids and 24 hour monitoring of turbidity
at the cooling water intakes (C6 and C7) shall be conducted.
4.3.25. The 24 hours monitoring of turbidty at the cooling water intakes (C6 and
C7) shall be established by setting up a continuous water quality monitoring station
in front of the intakes during the dredging activities. The monitoring system
include the turbidity sensor and data logger which is capable of data capturing at every 5 minutes. The data
sahll be downloaded daily and compared with the Action and Limit level determined
during the baseline water qualtiy monitoring at the cooling water intake
locations.
Additional Dissovled oxygen Monitoring FOR CULVERT L WATER DISCHARGE
FLOW
4.3.26.
In response to the Condition 2.18 of the
Environmental Permit no. EP-356/2009 requiring that a silt curtain /
impermeable barrier system be installed to channel water discharge flow from
Culvert L to locations outside the embayment area, a proposed replacement of
the requirement with additional dissolved oxygen monitoring has been conducted
at three monitoring stations, namely A, B and C between the eastern seawall of
Central Reclamation Phase III and the HKCEC Extension since November 2011 under
EP-356/2009 so that DO level between the eastern seawall of Central Reclamation
Phase II and the HKCEC extension could be continuously monitored.
4.3.27.
With respect to the commencement of dredging works under HK/2012/08 and
the installation of MTR precast protection unit, the enhanced water quality
monitoring for Culvert L was temporarily suspended since 24 July 2013
4.3.28. The monitoring of
dissolved oxygen are to be carried out once per week, at mid-flood and mid-ebb
tides for 3 water depths (1m below water surface, mid-depth and 1m above sea
bed, except where the water depth less than 6m, the mid-depth may be omitted.
If the water depth be equal to or less than 3m, only the mid-depth will be
monitored).
5.0.1.
The environmental monitoring will be
implemented based on the division of works areas of each designed project
managed under different contracts with separate FEP applied by individual
contractors. Overall layout showing work areas of various contracts, latest
status of work commencement and monitoring stations is shown in Figure 2.1 and Figure 4.1.
The monitoring results are presented in according to the Individual
Contract(s).
5.0.2.
In the reporting month, the concurrent
contracts are as follows:
Contract no. HK/2009/01 – Wan
Chai Development Phase II – Central-Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre; and
Contract no. HK/2009/02 Wan
Chai Development Phase II – Central-Wan Chai Bypass at Wan Chai East
Contract no. HY/2009/15 -
Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)
Contract no. HY/2009/19- Central-
Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
Contract no. HK/2012/08 – Wan
Chai Development Phase II – Central- Wan Chai Bypass at Wan Chai West
Contract no. HY/2010/08 –
Central- Wanchai Bypass Tunnel (Slip Road 8 Section)
5.0.3.
The environment monitoring schedules for
reporting month and coming month are presented in Appendix 5.1.
Contract no.
HK/2009/01 - Wan Chai Development Phase II – Central –Wanchai Bypass at HKCEC,
Contract no. HK/2009/02 - Wan Chai Development Phase II – Central – Wan Chai
Bypass at WanChai East
5.1.1.
The proposed division of noise monitoring
stations are summarized in Table 5.1 below.
Table 5.1 Noise Monitoring Station for Contract nos.
HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour Road Sports Centre |
5.1.2.
No action or limit level exceedance was
recorded in this reporting month.
5.1.3.
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 5.2.
Contract no. HY/2009/15 - Central-Wanchai
Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)
5.1.4.
The noise monitoring for HY/2009/15 was
commenced on 10 November 2010. The proposed division of noise monitoring
stations are summarized in Table 5.2 below.
Table 5.2 Noise
Monitoring Station for Contract no. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
5.1.5.
No action or limit level exceedance was recorded
in this reporting month.
5.1.6.
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no.
HY/2009/19- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern
Corridor Link
5.1.7.
The proposed division of noise monitoring
stations are summarized in Table 5.3 below.
Table 5.3 Noise
Monitoring Station for Contract no. HY/2009/19
Station |
Description |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist Church Henrietta Secondary
School |
5.1.8. School examination
was scheduled to be taken place at Henrietta Secondary School on 6 February
2017 to 21 February 2017, the limit level of noise monitoring at station M6 was
adjusted to 65dB(A) during examination period accordingly.
5.1.9.
Three limit level exceedances were recorded
at M6- HK Baptist Church Henrietta Secondary School on 07, 13 and 21 February
2017 in this reporting month.
5.1.10.
Traffic noise was observed during monitoring 07,
13 and 21 February 2017 and were considered as the major noise contribution. As
such, the limit level exceedance was concluded as non-project related.
5.1.11.
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 5.2.
Contract no.
HY/2010/08-Central-Wanchi Bypass Tunnel (Slip Road 8 Section)
5.1.12.
The proposed division of noise monitoring
stations are summarized in Table 5.4
below.
Table 5.4 Noise
Monitoring Station for Contract no. HY/2010/08
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
5.1.13.
No action or limit level exceedance was
recorded in this reporting month.
5.1.14.
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 5.2.
Contract no.
HK/2009/01 - Wan Chai Development Phase II – Central –Wanchai Bypass at HKCEC
5.2.1
Air monitoring was commenced on 1 April 2011
in response to the commencement of the land-filling work for Contract no.
HK/2009/01. The proposed divisions of air monitoring stations are summarized in
Table 5.5 below.
Table 5.5 Air
Monitoring Stations for Contract no. HK/2009/01
Station |
Description |
CMA5b |
Pedestrian Plaza |
CMA6a |
WDII PRE Site Office |
5.2.2
One 1hr TSP action level exceedance was
recorded at CMA5b on 02 February 2017.
5.2.3
No construction works was undertaken on 02
February 2017 around Pedestrian Plaza under Contract HK/2009/01, no particular
observation regarding air quality impact was observed during sampling. In view
of the above, the action level exceedance was considered to be non-project
related and potentially contributed by local ambient condition.
5.2.4
One 24hr TSP action level exceedance was recorded
at CMA5b on 18 February 2017.
5.2.5
No construction works was undertaken on 18
February 2017 around Pedestrian Plaza under Contract HK/2009/01, no particular
observation regarding air quality impact was observed during sampling. In view
of the above, the action level exceedance was considered to be non-project
related and potentially contributed by local ambient condition such as road
traffic next to the monitoring station.
5.2.6
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no.
HK/2009/02 - Wan Chai Development Phase II – Central – Wan Chai Bypass at
WanChai East
5.2.7
Air monitoring was commenced in mid-January
2011 for the land-filling work for Contract no. HK/2009/02. The proposed
division of air monitoring stations are summarized in Table 5.6
below.
Table 5.6 Air
Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention
of Cruelty to Animals |
5.2.8
No exceedance was recorded in the reporting
month. Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of
air monitoring results and graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/15 - Central-Wanchai
Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)
5.2.9
Air monitoring was commenced on 15 March 2011
for the land filling work for Contract no. HY/2009/15. The proposed division of
air monitoring stations are summarized in Table 5.7 below.
Table 5.7 Air
Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB PRE Site Office |
5.2.10
No exceedance was recorded in the reporting
month. Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of
air monitoring results and graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/19- Wan Chai Bypass Tunnel
(North Point Section) and Island Eastern Corridor Link
5.2.11
The proposed division of air monitoring
stations are summarized in Table 5.8 below.
Table 5.8 Air
Monitoring Stations for Contract no. HY/2009/19
Station |
Description |
CMA1b |
Oil Street Site Office |
CMA2a |
Causeway Bay Community Centre |
5.2.12
No exceedance was recorded in the reporting
month. Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of
air monitoring results and graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2012/08-
Wan Chai Development Phase II – Central-Wan Chai Bypass at Wan Chai West
5.2.13
The proposed division of air monitoring
stations are summarized in Table 5.9 below.
Table 5.9 Air Monitoring Stations for Contract no. HK/2012/08
Station |
Description |
CMA5b |
Pedestrian Plaza |
5.2.14
One 1hr TSP action level exceedance was
recorded at CMA5b on 02 February 2017.
5.2.15
Despite formwork erection and rebar fixing
was undertaken on 02 February 2017 around Pedestrian Plaza under Contract
HK/2012/08, no particular observation regarding air quality impact was observed
during sampling. In view of the above, the action level exceedance was
considered to be non-project related and potentially contributed by local
ambient condition.
5.2.16
One 24hr TSP action level exceedance was recorded
at CMA5b on 18 February 2017.
5.2.17
Despite formwork erection and rebar fixing
was undertaken on 18 February 2017 around Pedestrian Plaza under Contract
HK/2012/08, no particular observation regarding air quality impact was observed
during sampling. In view of the above, the action level exceedance was
considered to be non-project related and potentially contributed by local
ambient condition such as road traffic next to the monitoring station.
5.2.18
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no.
HY/2010/08- Central-Wanchai Bypass Tunnel (Slip Road 8 Section)
The proposed
division of air monitoring stations are summarized in Table 5.10 below.
Table 5.10 Air Monitoring Stations for Contract no. HY/2010/08
Station |
Description |
CMA3a |
CWB PRE Site Office |
5.2.19
No exceedance was recorded in the reporting
month. Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of
air monitoring results and graphical presentation can be referred in Appendix 5.3.
5.3.1.
Due to Chinese New Year Holiday and no marine
activities will be conducted under all WDII-CWB contracts according to the
information provided by the Contractor(s), the water quality monitoring event
at all WQM stations was temporary suspended on 28 January 2017 to 31 January
2017.
5.3.2.
With respect to the reinstatement of the silt
screen system for Cooling Water Intakes P7, P8, P9 and WSD Water Intake RW21,
the respective water quality monitoring was reverted to the previous monitoring
location for Water Quality Monitoring Station RW21-P789 from water quality
stations RW21-P789 East (RW21-P789E) and RW21-P789 West (RW21-P789W) from 25
January 2017 onwards.
5.3.3.
With respect to the temporarily suspension of
marine construction works at WCR3 Area by Contract HK/2009/02, the installed
silt screen for intake group (P7, P8, P9 and WSD21) was removed on 26 November
2016.
5.3.4.
As advised by the Contractor of HK/2009/01,
all silt screen remains removal works at P1, P3, P4, P5 and C1 water quality
monitoring stations were completed on 8 May 2016.
5.3.5.
With respect to the marine works undertaken
at WCR3 by Contract HK/2009/02, the respective water quality monitoring station
C1 associated with Contract HK/2009/01 was updated as in association with
Contract HK/2009/01 and Contract HK/2009/02.
5.3.6.
With respect to the marine works undertaken
at CBTS by Contract HY/2010/08, the respective water quality monitoring station
C7 associated with Contract HY/2009/15 was updated as in association with
Contract HY/2009/15 and Contract HY/2010/08.
5.3.7.
With respect to the marine works undertaken
at HKCEC2 by Contract HK/2012/08, the respective water quality monitoring
station WSD19, P1, P3, P4, and P5 were associated with Contract HK/2012/08.
Table 5.11 Water quality Monitoring Stations for contracts with
respect to remaining DP3 work areas after the completion of DP5 & DP6 in
2012 and intake diversion in 2013
Contract
No. |
Remaining
DP3 and work area(s) |
Relevant
Water quality monitoring Stations, |
Division of WQM w.r.t tentative works commenced / to be commenced |
HK/2009/01 |
WCR3 |
C11 |
Apr 2013 |
HK/2009/02 |
WCR3, WCR4, TWCR4 |
RW21-P7892, C11 |
Apr 2013 |
HK/2012/08 |
HKCEC2W, HKCEC2E |
WSD19, P13, P33,
P43, P53 |
Aug 2013 |
HY/2009/15 |
TCBR2, TCBR3, TCBR1W,
TPCWAE, TPCWAW |
C64, C7, Ex-WPCWA
SW, Ex-WPCWA SE (plus enhanced DO monitoring) |
Nov 2010 |
HY/2010/08 |
TCBR3, TCBR4 |
C64, C7 (plus enhanced DO monitoring) |
Mar 2014 |
Remarks:
1. The water quality
monitoring station C1 shall be associated with Contract No. HK/2009/02 upon
commencement of marine works under DP3 at WCR3 area.
2. 4 intakes (re-provisioned
Wanchai WSD intake, Great Eagle Centre, China Resources Centre & Sun Hung
Kai Centre constructed adjacent to each other) taken as a single group for silt
screen protection and monitoring. Re-provisioned intake reference: P1: HKCEC
Phase 1; P3: APA, P4: Shui On; P5: Government Buildings (Wanchai Tower /
Revenue Tower / Immigration Tower)
3. The water quality
monitoring stations for WSD19, P1, P3, P4, P5 shall be associated with Contract
No. HK/2009/01 prior to their transition to Contract HK/2012/08.
4. Enhanced DO Monitoring at
C6 since the intake abandon in May 2011.
5. With respect to the removal
of silt screen at WQM station RW21-P789 on 26 November 2016, the respective water
quality monitoring at RW21-P789 was adjusted to RW21-P789E and RW21-P789W since
28 November 2016 ebb-tide.
Contract no.
HK/2009/01 - Wan Chai Development Phase II – Central –Wanchai Bypass at HKCEC
5.3.10
Water quality monitoring for Contract no.
HK/2009/01 was commenced on 23 July 2010. The proposed division of water
quality monitoring stations are summarized in Table 5.12 below.
Table 5.12 Water quality monitoring Stations
for Contract no. HK/2009/01
Station Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
5.3.11
No action or limit level was recorded in this
reporting month.
5.3.12
Water quality monitoring results measured in
this reporting period are reviewed and summarized. Details of water quality
monitoring results and graphical presentation can be referred in Appendix 5.4.
Contract no.
HK/2009/02 - Wan Chai Development Wan Chai Development Phase II – Central – Wan
Chai Bypass at WanChai East
5.3.13
Water
quality monitoring for Contract no. HK/2009/02 was commenced on 8 July 2010.
The proposed division of water quality monitoring stations are summarized in Table
5.13 below.
Table 5.13 Water
quality Monitoring Stations for Contract no. HK/2009/02
Station Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
Cooling Water Intake / WSD
Salt Water Intake |
|||
RW21-P789 |
Great Eagle Centre/ Sun Hung
Kai Centre/ WSD Wanchai salt water
intake / China Resources Building |
836268.0 |
816020.0 |
5.3.14
There was 1 action level of turbidity
exceedances recorded at RW21-P789 on 02 February 2017.
5.3.15
After checking with the Contractor, no marine
activity was conducted on 02 February 2017 while installed silt screen was
generally in place. In view of the above, the exceedance was considered not
project related.
5.3.16
Water quality monitoring results measured in
this reporting period are reviewed and summarized. Details of water quality
monitoring results and graphical presentation can be referred in Appendix 5.4.
Contract no. HK/2012/08 - Wan Chai
Development Phase II – Central- Wan Chai Bypass at Wan Chai West
5.3.17
Water quality monitoring for Contract no.
HK/2012/08 was commenced on 5 March 2013. The proposed division of water
quality monitoring stations are summarized in Table 5.14 below.
Table 5.14 Water quality Monitoring Stations
for Contract no. HK/2012/08
Station
Ref. |
Location |
Easting |
Northing |
|
WSD Salt Water Intake |
||||
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
|
Cooling Water Intake |
||||
P1 |
HKCEC Phase I |
835774.7 |
816179.4 |
|
P3 |
The Academy of performing
Arts |
835824.6 |
816212.0 |
|
P4 |
Shui on Centre |
835865.6 |
816220.0 |
|
P5 |
Government
Buildings (Wanchai
Tower / Revenue Tower / Immigration Tower) |
835895.2 |
816215.2 |
|
5.3.18
There were 2 action level and 1 limit level
of turbidity exceedances recorded at WSD19 on 2 and 13 February 2017.
5.3.19
After checking with the Contractor, no marine
activity was conducted on 2 February 2017. In view of no marine construction
activity, the exceedance was considered not project related.
5.3.20
Despite trimming of rock mound profile was
conducted on 13 February 2017, Contractor mitigation measure including the use
of localized silt curtain was in place. Location of the construction area was
at downstream of monitoring station WSD19 during the monitoring period. In view
of the above, the exceedance was considered not project related.
5.3.21
There was one action level of suspended solid
exceedance recorded at P1 on 6 February 2017.
5.3.22
After checking with the Contractor, trimming of rock
mound profile near Zone B and earth works near Zone D were conducted on 06
February 2017 and Contractor mitigation measures including the use of localized
silt curtain was generally in place.
5.3.23
Nevertheless, muddy dispersion from a
potential outfall location was observed at the seawall boundary within the
HKCEC2E area (South of the monitoring Station P1) during monitoring period on 06
February 2017. Follow up site inspection was hence conducted on 07 February
2017 and it was identified that a water treatment facility for construction
site effluent from excavation works (Expo Drive West) in area under Contract
HK/2012/08 was in operation and the associated discharge point was identified
located at the upstream location of the observed outfall location. However, as
no direct information is available for the operation and discharge condition on
the monitoring date, it is therefore considered that no sufficient information
is available to conclude if the exceedance case would be related to Project
works.
5.3.24
In spite of the above findings, the
Contractor was reminded to maintain regular checking at the aforesaid discharge
location and the associated treatment facility to ensure the effective
operation and the operation condition and discharge quality of the aforesaid
water treatment unit will keep in view by ET/RSS.
5.3.25
Water quality monitoring results measured in
this reporting period are reviewed and summarized. Details of water quality
monitoring results and graphical presentation can be referred in Appendix 5.4.
Contract no. HY/2009/15 - Central-Wanchai
Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)
5.3.26
Due to the commencement of the maintenance
dredging on 10 November 2010, water quality monitoring for Contract no.
HY/2009/15 was commenced on 9 November 2010. The proposed division of water
quality monitoring stations are summarized in Table 5.15 and Table 5.16 below.
Table 5.15 Water quality monitoring Stations
for Contract no. HY/2009/15
Station Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C7 |
Windsor House |
837193.7 |
816150.0 |
- The
cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the
water quality monitoring at C6 was then terminated since 17 May 2011.
Table 5.16 Enhance Dissolved Oxygen Monitoring Stations for Contract no.
HY/2009/15
Station Ref. |
Location |
C6 |
Excelsior Hotel |
Ex-WPCWA SW |
South-western of
the ex-Wan Chai Public Cargo Working Area |
Ex-WPCWA-SE |
South-eastern of
the ex-Wan Chai Public Cargo Working Area |
Remarks:
1.
Enhanced DO monitoring at Windsor House Cooling (Station Ref: C7) was
temporarily suspended since 22 October 2014 with respect to the formation of
temporary reclamation zone TS3 and to be resumed upon removal of the respective
temporary reclamation zone.
5.3.27
There was 1 limit level of turbidity
exceedances recorded at C7 on 13 February 2017.
5.3.28
After checking with the Contractor, no marine
activity was conducted on 13 February 2017 at Causeway Bay Typhoon Shelter. In
view of no marine construction activity, the exceedances were considered not
project related.
5.3.29
There was 1 action level of DO exceedances
recorded at Ex-WPCWA SE on 2 February 2017.
5.3.30
After checking with the Contractor, no marine
construction activities was conducted at TPCWA on 2 February 2017 while
upstream discharge from nearby culvert was noted. In view of the above, the
exceedance was considered not related to Project works.
5.3.31
Water quality monitoring results measured in
this reporting period are reviewed and summarized. Details of water quality
monitoring results and graphical presentation can be referred in Appendix 5.4.
Contract no. HY/2010/08- Central-Wanchai
Bypass Tunnel (Slip Road 8 Section)
5.3.32
The proposed division of water quality
monitoring stations are summarized in Table 5.17 and Table 5.18 below:
Table 5.17 Water
quality monitoring Stations for Contract no. HY/2010/08
Station Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C7 |
Windsor House |
837193.7 |
816150.0 |
Table 5.18
Enhance Dissolved Oxygen Monitoring Stations for Contract no. HY/2010/08
Station Ref. |
Location |
C6 |
Excelsior Hotel |
Remarks:
1.
Enhanced DO monitoring at Windsor House Cooling (Station Ref: C7) was
temporarily suspended since 22 October 2014 with respect to the formation of
temporary reclamation zone TS3 and to be resumed upon removal of the respective
temporary reclamation zone.
5.3.33
There was 1 limit level of turbidity
exceedances recorded at C7 on 13 February 2017.
5.3.34
After checking with the Contractor, no marine
activity was conducted on 13 February 2017, and the installed silt screen was
in place. In view of no marine construction activity, the exceedances were
considered not project related.
5.3.35
Water quality monitoring results measured in
this reporting period are reviewed and summarized. Details of water quality
monitoring results and graphical presentation can be referred in Appendix 5.4.
Contract no.
HK/2009/01 - Wan Chai Development Phase II – Central –Wanchai Bypass at HKCEC
5.4.1.
No inert C&D waste and non- inert C&D
waste disposed in this reporting month. Details of the waste flow table are
summarized in Table 5.19.
Table 5.19 Details
of Waste Disposal for Contract no. HK/2009/01
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL |
62116.405 |
TKO137, TM38 |
Inert C&D materials recycled, m3 |
NIL |
5856.5 |
N/A |
Non-inert C&D materials disposed, m3 |
NIL |
1673.69 |
SENT Landfill |
Non-inert C&D materials recycled, kg |
NIL |
203993 |
N/A |
Chemical waste disposed, kg |
NIL |
10250 |
N/A |
Marine Sediment (Type 1 – Open Sea
Disposal), m3 |
NIL (Bulk Volume) |
97428.2 (Bulk Volume) |
South of Cheung Chau |
Marine Sediment (Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3 |
NIL (Bulk
Volume) |
52250 (Bulk
Volume) |
East of Cha Chau |
Dredged Sediment
Requiring Type 3 – Special Treatment / Disposal contained in Geosynthetic
Containers |
NIL (Bulk Volume) |
6773 (Bulk Volume) |
East
of Cha Chau |
5.4.2.
There were no marine sediment Type 1- Open
Sea Disposal and no marine sediments Type 1 – Open Sea Disposal (Dedicate
Sites) & Type 2 – Confined Marine Disposal disposed in this reporting month.
Contract no.
HK/2009/02 - Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai
East
5.4.3.
No inert C&D waste and Non-inert C&D
waste disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.20.
Table 5.20 Details
of Waste Disposal for Contract no. HK/2009/02
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials
disposed, m3 |
NIL |
276075.1 |
TKO137 / TM 38 |
Inert C&D materials
recycled, m3 |
NIL |
18161 |
N/A |
Non-inert C&D materials
disposed, m3 |
NIL |
1515.103 |
SENT Landfill |
Non-inert C&D materials
recycled, m3 |
N/A |
N/A |
N/A |
Chemical waste disposed, kg |
NIL |
13860 |
SENT Landfill |
Marine Sediment (Type 1 –
Open Sea Disposal), m3 |
NIL |
240222 (Bulk volume) |
South of Cheung Chau |
Marine Sediment (Type 1 –
Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal) ,
m3 |
NIL |
146445 (Bulk volume) |
East of Sha Chau |
5.4.4.
There were no marine sediment Type 1 – Open
Sea Disposal and no Type 1 Open Sea Disposal (Dedicate Sties) & Type 2 – Confined Marine Disposal disposed in this
reporting month.
Contract no.
HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter
Section)
5.4.5.
No Inert and non-inert C&D material was
recycled in this reporting month. Details of the waste flow table are summarized
in Table 5.21
Table 5.21 Details
of Waste Disposal for Contract no. HY/2009/15
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Remarks |
Inert C&D materials disposed, m3 |
NIL |
141579.2 |
Tuen Mun Area 38 |
NIL |
NIL |
65216 |
TKO137 FB |
NIL |
|
Inert C&D materials recycled, m3 |
NIL |
8127.21 |
HY/2010/08 |
NIL |
NIL |
304 |
Ex-PCWA |
NIL |
|
NIL |
111.9 |
TS4 |
NIL |
|
Non-inert C&D materials disposed, m3 |
NIL |
252.2 |
SENT Landfill |
NIL |
Non-inert C&D materials
recycled, kg |
NIL |
299361.5 |
N/A |
NIL |
Chemical waste disposed, kg |
NIL |
8,200 |
N/A |
NIL |
Marine Sediment (Type 1 –
Open Sea Disposal), m3 |
NIL (Bulk Volume) |
156909 (Bulk Volume) |
Cheung Chau South |
Dredging from TCBR1E /
TCBR1W / TCBR2/ TCBR3 / TCBR4 / Maintenance dredging |
Marine Sediment (Type 1 –
Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal) ,
m3 |
NIL (Bulk Volume) |
327746 (Bulk Volume) |
East of Sha Chau / South of
the Brothers |
Dredging from TCBR1E /
TCBR1W / TCBR2/ TCBR3 / TCBR4 / Maintenance dredging |
Marine Sediment (Type 3 – Special Treatment / Disposal contained in
Geosynthetic Containers) m3 |
NIL (Bulk Volume) |
12640 (Bulk Volume) |
East of Sha Chau / South of
the Brothers |
Dredging from TCBR1W /
Maintenance dredging |
Marine Sediment (Type 2 – Confined Marine Disposal), m3 |
NIL |
9350 (Bulk Volume) |
East of Sha Chau |
Dredging from Eastern
Breakwater of CBTS |
Marine Sediment (Type 1 –
Open Sea Disposal) , m3 |
NIL (Bulk Volume) |
600 (Bulk Volume) |
East Sha Chau / South of The
Brothers |
Dredging
from Phase 3 Mooring Re-arrangement |
Marine Sediment (Type 2– Confined
Marine Disposal) , m3 |
NIL (Bulk Volume) |
14,780 (Bulk Volume) |
South of The Brothers |
Dredging
from Phase 3 Mooring Re-arrangement |
Marine Sediment (Type 3 – Special
Treatment / Disposal contained in Geosynehetic Containers) , m3 |
NIL (Bulk Volume) |
2,760 (Bulk Volume) |
South of The Brothers |
Dredging
from Phase 3 Mooring Re-arrangement |
5.4.6.
There was no Type 1 Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal and Type 1 Open
Sea Disposal disposed in this reporting month.
Contract no. HY/2009/19
–Central- WanChai Bypass Tunnel (North Point Section) and Island Eastern
Corridor Link
5.4.7.
No inert C&D waste and non-inert C&D
waste disposed in this reporting month. Details of the waste flow table are
summarized in Table 5.22.
Table 5.22 Details of
Waste Disposal for Contract no. HY/2009/19
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL |
355921.04 |
TM38 |
Inert C&D materials recycled, m3 |
NIL |
59367 |
N/A |
Non-inert C&D materials disposed, m3 |
NIL |
1068.6 |
N/A |
Non-inert C&D materials recycled, kg |
NIL |
333.14 |
N/A |
Chemical waste disposed, L |
NIL |
2.12 |
N/A |
Marine Sediment (Type 1 – Open Sea
Disposal), m3 |
NIL |
162 |
South Cheung Chau |
Marine Sediment (Type 2 – Confined Marine
Disposal) , m3 |
NIL |
681 |
East Sha Chau |
Marine Sediment (Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3 |
NIL |
4976.00 |
East Sha Chau |
5.4.8.
There was no marine sediment Type1- Open Sea
Disposal and there was no Type 1 – Open Sea Disposal (Dedicate Sites) &
Type 2 – Confined Marine Disposal disposed in this reporting month.
Contract no. HK/2012/08
–Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan Chai West
5.4.9.
There was no Inert C&D waste disposed and
no non-inert C&D waste disposed in this reporting month. Details of the
waste flow table are summarized in Table 5.23.
Table 5.23 Details of Waste Disposal for Contract no. HK/2012/08
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials
disposed, m3 * |
NIL |
4131 |
TM38 |
|
NIL |
273 |
TKO137 |
Inert C&D materials
recycled, m3 |
NIL |
NIL |
N/A |
Non-inert C&D materials
disposed, m3 |
NIL |
315 |
N/A |
Non-inert C&D materials
recycled, kg |
NIL |
NIL |
N/A |
Chemical waste disposed, L |
NIL |
NIL |
N/A |
Marine Sediment (Type 1 –
Open Sea Disposal), m3 |
NIL (Bulk volume) |
31759 (Bulk volume) |
South of Cheung Chau |
Marine Sediment (Type 1 –
Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal) ,
m3 |
NIL (Bulk volume) |
108542 (Bulk volume) |
South of The Brothers (from 27 Aug 2013 onwards) |
5.4.10.
There was no Marine Sediment Type 1 – Open Sea
Disposal (Delicate Sites) & Type 2 – Confined Marine Disposal and Marine
Sediment Type 1 – Open Sea Disposal disposed in this reporting month.
Contract no. HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip
Road 8)
5.4.11.
No inert C&D and no non-inert C&D
waste disposed in this reporting month. Details of the waste flow table are
summarized in Table 5.24
Table 5.24 Details of
Waste Disposal for Contract no. HY/2010/08
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials
disposed, m3 |
NIL NIL |
26849.2 19739.4 |
TM38 TKO137 |
Inert C&D materials
recycled, m3 |
NIL |
NIL |
N/A |
Non-inert C&D materials
disposed, m3 |
NIL |
NIL |
N/A |
Non-inert C&D materials
recycled, kg |
NIL |
NIL |
N/A |
Chemical waste disposed, L |
NIL |
NIL |
N/A |
Marine Sediment (Type 1 –
Open Sea Disposal) |
NIL |
62559.4 |
South Cheung Chau / Brothers
Island * |
Marine Sediment (Type 1 –
Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine disposal) |
NIL |
28309.2 |
Brothers Island |
Marine Sediment (Type 3 –
Special Treatment) |
NIL |
7780 |
Brothers Island |
5.4.12.
There were no Type 1 – Open Sea Disposal and
no Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine
Disposal disposed in this reporting month, and no Type 3- Special Treatment
disposed in this reporting month.
6.0.1.
The Event Action Plan for construction noise,
air quality and water quality are presented in Appendix 6.1.
Contract no. HK/2009/01 - Wan
Chai Development Phase II – Central –Wanchai Bypass at HKCEC
6.1.1
No action or limit level exceedance was
recorded in this reporting month.
Contract no. HK/2009/02 - Wan Chai Development Phase II –
Central – Wan Chai Bypass at WanChai East
6.1.2
No action or limit level exceedance was
recorded in this reporting month.
Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel
(Causeway Bay Typhoon Shelter Section)
6.1.3
No exceedance was recorded in the reporting
month.
Contract no. HY/2009/19 – Central – Wanchai
Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
6.1.6.
Three limit level exceedances were recorded
at M6- HK Baptist Church Henrietta Secondary School on 07, 13 and 21 February
2017 in this reporting month.
6.1.7.
Traffic noise was observed during monitoring
07, 13 and 21 February 2017 and were considered as the major noise
contribution. As such, the limit level exceedance was concluded as non-project
related.
Contract no. HY/2010/08 – Central-Wanchai Bypass – Tunnel (Slip Road 8
Section)
6.1.8.
No exceedance was recorded in the reporting
month.
Contract no. HK/2009/01 - Wan
Chai Development Phase II – Central –Wanchai Bypass at HKCEC
6.2.1
One 1hr TSP action level exceedance was
recorded at CMA5b on 02 February 2017.
6.2.2
No construction works was undertaken on 02
February 2017 around Pedestrian Plaza under Contract HK/2009/01, no particular
observation regarding air quality impact was observed during sampling. In view of
the above, the action level exceedance was considered to be non-project related
and potentially contributed by local ambient condition.
6.2.3
One 24hr TSP action level exceedance was recorded
at CMA5b on 18 February 2017.
6.2.4
No construction works was undertaken on 18
February 2017 around Pedestrian Plaza under Contract HK/2009/01, no particular
observation regarding air quality impact was observed during sampling. In view
of the above, the action level exceedance was considered to be non-project
related and potentially contributed by local ambient condition such as road
traffic next to the monitoring station.
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)
6.2.5
No exceedance was recorded in the reporting
month.
Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel
(Causeway Bay Typhoon Shelter Section)
6.2.6
No exceedance was recorded in the reporting
month.
Contract no. HY/2009/19 – Central – Wanchai
Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
6.2.7
No exceedance was recorded in the reporting
month.
Contract no. HK/2012/08 Wan Chai Development
Phase II - Central-Wan Chai Bypass at Wan Chai West
6.2.8
One 1hr TSP action level exceedance was
recorded at CMA5b on 02 February 2017.
6.2.9
Despite formwork erection and rebar fixing
was undertaken on 02 February 2017 around Pedestrian Plaza under Contract
HK/2012/08, no particular observation regarding air quality impact was observed
during sampling. In view of the above, the action level exceedance was considered
to be non-project related and potentially contributed by local ambient
condition.
6.2.10
One 24hr TSP action level exceedance was recorded
at CMA5b on 18 February 2017.
6.2.11
Despite formwork erection and rebar fixing
was undertaken on 18 February 2017 around Pedestrian Plaza under Contract
HK/2012/08, no particular observation regarding air quality impact was observed
during sampling. In view of the above, the action level exceedance was
considered to be non-project related and potentially contributed by local
ambient condition such as road traffic next to the monitoring station.
Contract no. HY/2010/08 –
Central-Wanchai Bypass – Tunnel (Slip Raod 8 Section)
6.2.12
No exceedance was recorded in the reporting
month.
Contract no. HK/2009/01 - Wan
Chai Development Phase II – Central –Wanchai Bypass at HKCEC
6.3.1
No action or limit level exceedance
was recorded in this reporting month.
Contract no. HK/2009/02 - Wan
Chai Development Phase II – Central – Wan Chai Bypass at WanChai East
6.3.2
There was 1 action level of turbidity
exceedances recorded at RW21-P789 on 02 February 2017.
6.3.3
After checking with the Contractor, no marine
activity was conducted on 02 February 2017 while installed silt screen was
generally in place. In view of the above, the exceedance was considered not
project related.
Contract no. HY/2009/15 -
Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)
6.3.4
There was 1 limit level of turbidity
exceedances recorded at C7 on 13 February 2017.
6.3.5
After checking with the Contractor, no marine
activity was conducted on 13 February 2017 at Causeway Bay Typhoon Shelter. In
view of no marine construction activity, the exceedances were considered not
project related.
6.3.6
There was 1 action level of DO exceedances
recorded at Ex-WPCWA SE on 2 February 2017.
6.3.7
After checking with the Contractor, no marine
construction activities was conducted at TPCWA on 2 February 2017 while
upstream discharge from nearby culvert was noted. In view of the above, the
exceedance was considered not related to Project works.
Contract no. HY/2009/19-
Central- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern
Corridor Link
6.3.8
No action or limit level exceedance was
recorded in this reporting month.
Contract no. HK/2012/08- Wan
Chai Development Phase II – Central- Wan Chai Bypass at Wan Chai West
6.3.9
There were 2 action level and 1 limit level
of turbidity exceedances recorded at WSD19 on 2 and 13 February 2017.
6.3.10
After checking with the Contractor, no marine
activity was conducted on 2 February 2017. In view of no marine construction
activity, the exceedance was considered not project related.
6.3.11
Despite trimming of rock mound profile was
conducted on 13 February 2017, Contractor mitigation measure including the use
of localized silt curtain was in place. Location of the construction area was
at downstream of monitoring station WSD19 during the monitoring period. In view
of the above, the exceedance was considered not project related.
6.3.12
There was one action level of suspended solid
exceedance recorded at P1 on 6 February 2017.
6.3.13
After checking with the Contractor, trimming of rock
mound profile near Zone B and earth works near Zone D were conducted on 06
February 2017 and Contractor mitigation measures including the use of localized
silt curtain was generally in place.
6.3.14
Nevertheless, muddy dispersion from a
potential outfall location was observed at the seawall boundary within the
HKCEC2E area (South of the monitoring Station P1) during monitoring period on 06
February 2017. Follow up site inspection was hence conducted on 07 February
2017 and it was identified that a water treatment facility for construction
site effluent from excavation works (Expo Drive West) in area under Contract
HK/2012/08 was in operation and the associated discharge point was identified
located at the upstream location of the observed outfall location. However, as
no direct information is available for the operation and discharge condition on
the monitoring date, it is therefore considered that no sufficient information
is available to conclude if the exceedance case would be related to Project
works.
6.3.15
In spite of the above findings, the
Contractor was reminded to maintain regular checking at the aforesaid discharge
location and the associated treatment facility to ensure the effective operation
and the operation condition and discharge quality of the aforesaid water
treatment unit will keep in view by ET/RSS.
Contract no. HY/2010/08 –Central
- Wan Chai Bypass (CWB) –Tunnel (Slip Road 8)
6.3.16
There was 1 limit level of turbidity
exceedances recorded at C7 on 13 February 2017.
6.3.17
After checking with the Contractor, no marine
activity was conducted on 13 February 2017, and the installed silt screen was
in place. In view of no marine construction activity, the exceedances were
considered not project related.
6.4.1
There was no non-compliance from the site
audits in the reporting period. The observations and recommendations made in
each individual site audit session were presented in Section 8.
6.4.2
No non-compliances from monitoring was
recorded in reporting month.
6.5.1
There was no particular action taken since no
non-compliance was recorded from the site audit in the reporting period.
7.0.1.
According to Condition 3.4 of the
EP-356/2009, this section addresses the relevant cumulative construction impact
due to the concurrent activities of the current projects including the Central
Reclamation Phase III, Central-Wanchai Bypass and Island Eastern Corridor Link
projects.
7.0.3.
According to the construction programme of
Central-Wanchai Bypass at Wanchai West at the Central Reclamation Phase III
area include road works, backfilling works and reinstatement of Culvert and
Cooling main were performed in February 2017 reporting month. As no project
related exceedance were recorded during the reporting period, cumulative
construction impact due to the concurrent activities of the current projects
with the Central Reclamation Phase III (CRIII) was considered as insignificant.
7.0.4.
According to the construction programme of Wan Chai Development Phase
II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects, the
major construction activities under Wan Chai Development Phase II were, road
and drains, building demolition and tunnel works at Wan Chai East, tunnel
construction and backfilling works and ELS works at Wan Chai West. The major
construction activities under Central-Wan Chai Bypass and Island Eastern
Corridor Link Projects were road works and ventilation building construction at
Central Interchange, reinstatement of Eastern Breakwater, ELS works and
retaining wall construction at Victoria Park, ELS works and tunnel works at
TS3, bridge construction, piling and tunnel works at North Point area in the
reporting month. In addition, other non-Wan Chai Development Phase II,
Central-Wan Chai Bypass and Island Eastern Corridor Link projects was
observed undertaken at Wan Chai North and North Point area.
7.0.5.
No significant air impact from construction
activities was anticipated in the reporting month. Besides, no project related
exceedance was recorded during the air and noise environmental monitoring
events in the reporting month. Thus, it is evaluated that the cumulative
construction impact from the concurrent projects including Central Reclamation
Phase III (CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass
(CWB), Island Eastern Corridor Link projects (IECL) was insignificant.
8.0.1. During this
reporting month, weekly environmental site audits were conducted for Contracts
no. HK/2009/01, HK/2009/02,
HY/2009/15, HY/2009/19, HK/2012/08 and HY/2010/08. No non-conformance was
identified during the site audits.
8.0.2. Four site inspections for Contract no. HK/2009/01 were conducted on 1, 8, 16
and 22 February 2017 in reporting month. There was no particular findings
observed in this reporting month.
8.0.3. Four site
inspections for Contract no. HK/2009/02 were carried out on 1, 9, 16 and 21
February 2017 in reporting month. Results of these inspections and outcomes are
summarized in Table 8.2.
Table 8.2 Summary
of Environmental Inspections for Contract no. HK/2009/02
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
170216_1 |
16 Feb 2017 |
Proper NRMM Label with correct information
shall be provided to powered mechanical equipment (Portion 3 & 4) |
Proper NRMM label was provided at the
captioned mechanical machine at Portion 3 & 4. |
Completion as observed on 21 February 2017. |
8.0.4. Four site
inspections for Contract no. HY/2009/15 were carried out on 2, 7, 14 and 21
February 2017 in reporting month. Results of these inspections and outcomes are
summarized in Table 8.3.
Table
8.3 Summary of
Environmental Inspections for Contract no. HY/2009/15
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
170214_1 |
14 Feb 2017 |
Refuse sitting on the edge of breakwater shall be
cleaned regularly (Eastern Breakwater) |
Refuses sitting on the edge of breakwater was cleaned |
Completion as observed on 21 Feb 2017 |
8.0.6. Four site
inspections for Contract no. HK/2012/08 were carried out on 1, 7, 14, 21
February 2017 in this reporting period. Results of these inspections and
outcomes are summarized in Table 8.5.
Table 8.5 Summary of Environmental
Inspections for Contract no. HK/2012/08
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
170201_01 |
1-Feb-17 |
Contractor
is needed to review the operation process of the concerned concrete machine
near MVB area and provide necessary action to prevent dust emission to nearby
sensitive receiver. |
The
concerned machinery has been reviewed by the contractor and it is operating
at a controlled manner. No related dust emission was further observed. |
Completion
as observed on 7 Feb 2017. |
8.0.7. Four site
inspections for Contract no. HY/2010/08 were carried out on 1, 10, 15 and 22
February 2017 in this reporting period. Results of these inspections and
outcomes are summarized in Table 8.6.
Table 8.6 Summary of Environmental
Inspections for Contract no. HY/2010/08
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
170210_1 |
10 Feb 2017 |
Dust mitigation shall be provided to breaking works to avoid dust
emission (Victoria Park) |
No further breaking works was observed |
Completion as observed on 15 Feb 2017 |
170210_2 |
10 Feb 2017 |
Proper drip tray with sides shall be provided for chemical containers
(TS3) |
Drip tray was provided to chemical container |
Completion as observed on 15 Feb 2017 |
170215_1 |
15 Feb 2017 |
Embankment and protection along site boundary shall be reinforce to
avoid surface runoff to public area (TS3) |
No further surface runoff was observed |
Completion as observed on 22 Feb 2017 |
170215_2 |
15 Feb 2017 |
Proper covering shall be provided to stockpile and dust suppression
measure shall be provided during operation (Victoria Park) |
Covering was provided to stockpile stored on-site |
Completion as observed on 22 Feb 2017 |
170222_1 |
22 Feb 2017 |
NRMM Label shall be provided to powered mechanical equipment (TS3) |
NRMM Label was provided to the concerned PME |
Completion as observed on 2 Mar 2017 |
9.0.1.
There was no environmental complaint received
in this reporting month.
9.0.2.
The details of cumulative complaint log and
updated summary of complaints are presented in Appendix 9.1
9.0.3.
Cumulative statistic on complaints and
successful prosecutions are summarized in Table 9.1 and Table
9.2 respectively.
Table 9.1 Cumulative
Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement
works (Mar 2010) to last reporting month |
47 |
February 2017 |
0 |
Total |
47 |
Table 9.2 Cumulative
Statistics on Successful Prosecutions
Environmental Parameters |
Cumulative No. Brought
Forward |
No. of Successful
Prosecutions this month (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1.
The EM&A programme was carried out in
accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
10.0.2.
The scheduled construction activities and the
recommended mitigation measures for the coming month are listed in Table
10.1.
Table 10.1 Construction Activities
and Recommended Mitigation Measures in Coming Reporting Month
Contract No. |
Key Construction Works |
Recommended Mitigation
Measures |
HK/2009/01 |
·
Nil |
·
Nil |
HK/2009/02 |
·
Nil |
·
Daily visual
inspection of silt screen and silt curtain to ensure its operation properly. ·
Implement
silt curtain in accordance with the associated plans submitted to EPD. |
HY/2009/15 |
·
Nil |
·
Daily visual
inspection of silt screen and silt curtain to ensure its operation properly ·
Implement silt curtain in accordance with the associated plans
submitted to EPD. |
HY/2009/19 |
·
Nil |
·
Nil |
HK/2012/08 |
·
Construction of Box 1 unit ·
Construction of culvert L Bay 8 |
·
To conform
the installation and setting as in the silt screen and silt curtain
deployment plan ·
To space out noisy equipment and position as far as possible from
sensitive receiver. ·
Daily visual
inspection of silt screen and silt curtain to ensure its operation properly |
HY/2010/08 |
·
Diversion pipe maintenance ·
Preparation for Diaphragm Wall Removal
Works |
·
To conform
the installation and setting as in the silt screen and silt curtain
deployment plan ·
Daily visual
inspection of silt screen and silt curtain to ensure its operation properly |